TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: March 5, 2024

Title
ITEM(S) A1, MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE PLAN FOR NE 4th AVE/NE 1st ST

Body
Recommended Action:
Recommendation
Consideration of the following items:
Per LDR 7.1(C) (1)
Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2 , 10-20-20)
Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2 , 10-20-20)
Having exceeded the allowable 14 days throughout the course of construction the following Maintenance of Traffic plans are petitioning additional closures as follows:

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
Item(S) A

Item A1 - Pike - Motion to approve and accept a Maintenance of Traffic/ Road closure Plan for NE 4th Ave/ NE 1st St.

Body
Background:

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES

Item A1

Consider acceptance of a Maintenance of Traffic Plan by Pike to variable locations along NE 4th Ave/ NE 1st St. and adjacent alleys over the course of three months to allow the installation of larger concrete poles which require the use of a crane and outriggers for stability to properly set the new electrical poles for FPL infrastructure storm hardening projects.

Per LDR 7.1(C) (1) Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or ...

Click here for full text