TO:                                           CRA Board of Commissioners

FROM:                      Christine Tibbs

THROUGH:  Renée A. Jadusingh, Executive Director

DATE:                      September 1, 2022

 

98 NW 5th AVENUE RENOVATION - RELOCATION OF OVERHEAD UTILITY LINES TO UNDERGROUND

 

Recommended Action:

Approve the costs associated with removing the AT&T, Comcast, and FPL overhead utility lines and relocate them underground.

 

Background:

 

On May 25, 2021, the CRA Board awarded ITB 2021-03 for the renovation of 98 NW 5th Avenue (Project) to Waypoint Contracting, Inc. (Waypoint) and an Agreement between the CRA and Waypoint was executed on October 20, 2021 (Agreement.) 

 

The design of the Project necessitates removal of overhead utility lines that currently go across the front of the property facing NW 1st Street and relocating the lines underground. Along, with the relocation, new transformers will be installed to better service the needs of the Project, neighboring properties, and any future development in the area. Finally, new and more resilient concrete pole infrastructure will be installed.

 

CRA staff, Waypoint, the CRA’s Architect Synalovski, Romanik, and Saye, and the utility companies - AT&T, Comcast, and FPL - have had numerous discussions related to the removal and relocation of the overhead utility lines. All work related to the removal and relocation of the utility lines will be performed by the utility companies and payment will be remitted directly to the utility companies.

 

Cost of Removing and Relocating Utility Lines, Installing New Transformers and Concrete Poles:

 

Utility Company

Cost

AT&T

$102,785.28

Comcast

$7993.40

FPL

$55,664.27

TOTAL COST:

 $166,442.95

 

At this time, CRA Staff is requesting the CRA Board approve this request in the total amount of $166,442.95. to remove the AT&T, Comcast, and FPL overhead utility lines and relocate them underground. 

 

 

 

 

Attachments: Exhibit A - Location Map; Exhibit B - AT&T Relocation Costs; Exhibit C - Comcast Relocation Costs; Exhibit D - FPL Relocation Costs

 

CRA Attorney Review:

N/A

 

Finance Review:

N/A

 

Funding Source/Financial Impact:

Funds allocated from General Ledger # 6208B - 98 NW 5th Avenue Renovation- Construction

 

Overall need within the Community Redevelopment Area from Delray Beach CRA Redevelopment Plan: 

Removal of Slum And Blight                      

Land Use

Economic Development

Affordable Housing                     

Downtown Housing

Infrastructure

Recreation and Cultural Facilities