Title: APPROVAL OF AN ADDITIONAL SPENDING REQUEST AND CONTRACT INCREASE WITH REP SERVICES, INC. FOR PARK EQUIPMENT AND PARTS IN THE AMOUNT OF $32,100.00 FOR A REVISED TOTAL OF $191,665.45.
Sponsors: Parks & Recreation Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. Signed Additional Spending P2025-041, 3. PROPOSAL - Recycling Lids, 4. PROPOSAL - Benches, 5. Executed Agreement P2025-041, 6. Original Solicitation, 7. Clay County Contract
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners

FROM:                     Samuel Metott, Director, Parks and Recreation

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     May 5, 2026

 

Title

APPROVAL OF AN ADDITIONAL SPENDING REQUEST AND CONTRACT INCREASE WITH REP SERVICES, INC. FOR PARK EQUIPMENT AND PARTS IN THE AMOUNT OF $32,100.00 FOR A REVISED TOTAL OF $191,665.45.

 

Body

Recommended Action:

Recommendation

Motion to approve an additional spending request and a contract increase to agreement P2025-041 with REP Services, Inc. for Park Equipment and Parts in the amount of $32,100.00 for a revised total of $191,665.45.

 

Body

Background:

On September 15, 2025, the City Commission approved Resolution No. 185-25 authorizing a Master Contractor/Services Agreement with REP Services, Inc. for Park Equipment and Parts utilizing Clay County ITB 23/24-074 in the Amount of $134,865.69 for a Pavilion replacement at Mike Machek Park.

 

It was determined that the existing concrete slab required replacement to properly support the pavilion installation, and the original quote did not account for a concrete slab replacement.

 

On December 8, 2025, the City Commission approved an additional spending request and contract increase to accommodate the slab replacement and complete the pavilion installation.

 

These improvements were funded through the voter approved General Obligation (GO) Bond allocated for park enhancement projects

 

The Parks and Recreation Department requests an increase to its contract to purchase benches needed to complete the Main Beach Pavilion reconstruction at the Municipal Beach.  The request also includes replacement lids for beach trash receptacles that have reached the end of their useful life.

 

This motion in is accordance with the City Code of Ordinances, Section 36.02 and City Policies and Procedures, Change Orders and Amendments.

 

 

Original Request

$159,565.45

Additional Spending

$  32,100.00

 TOTAL:

$191,665.45

 

ATTACHMENTS:

1.                     Signed Additional Spending P2025-041

2.                     PROPOSAL - Recycling Lids

3.                     PROPOSAL - Benches

4.   Agreement

5.   Solicitation

6.   Contract

 

 

City Attorney Review:

N/A

 

Funding Source/Financial Impact:

$24,100.00; 001-72-734-572.46-40; Parks and Recreation; Repair and Maintenance

$  8,000.00; 433-34-000-534.49-97; Neighborhood Community Service; Sanitation

 

Timing of Request:

Timely approval is requested to complete in time for season.