Legislation Details

File #: 26-1328    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 10/8/2026 In control: City Commission
On agenda: 11/2/2026 Final action:
Title: APPROVAL OF A MAINTENANCE OF TRAFFIC PLAN / ROAD CLOSURE PLAN FOR THE INSTALLATION OF DECORATIVE CROSSWALKS ON SIDE STREETS ALONG NORTH SWINTON AVE FROM NE/NW 6TH STREET TO NE/NW 13TH STREET FOR THE N. SWINTON AVENUE ROADWAY & UNDERGROUND UTILITY IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 19-012)
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. MOT Plan - N. Swinton Avenue Roadway & Underground Utility Improvements (19-012)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners                                   

FROM:                     Missie Barletto, Public Works Director

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     November 2, 2026

 

Title

APPROVAL OF A MAINTENANCE OF TRAFFIC PLAN / ROAD CLOSURE PLAN FOR THE INSTALLATION OF DECORATIVE CROSSWALKS ON SIDE STREETS ALONG NORTH SWINTON AVE FROM NE/NW 6TH STREET TO NE/NW 13TH STREET FOR THE N. SWINTON AVENUE ROADWAY & UNDERGROUND UTILITY IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 19-012)

 

Body

Recommended Action:

Recommendation

Motion to Approve a Maintenance of Traffic Plan / Road Closure Plan for the installation of decorative crosswalks on side streets from NE/NW 6th Street to NE/NW 13th Street pursuant to ITBC No. 2024-010 for the N. Swinton Ave Roadway & Underground Utility Improvements Project. Having exceeded the allowable 14 days throughout the course of construction, All County Paving is requesting a Maintenance of Traffic Plan pursuant to LDR 7.1.8:

 

(C) Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2 <https://library.municode.com/fl/delray_beach/codes/land_development_regulations_?nodeId=CH2ADPR>, 10-20-20)

 

(1)  Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2 <https://library.municode.com/fl/delray_beach/codes/land_development_regulations_?nodeId=CH2ADPR>, 10-20-20)

 

Body

Background:

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES

All County Paving, the construction contractor for the N. Swinton Ave Roadway & Underground Utility Improvements Project, has submitted a MOT proposing the closure of side streets along N. Swinton Avenue in eight (8) work zone segments. This plan considers closing two streets at a time. The eight (8) work zone segments are as follows:

 

Work Zone #1

NW 6th Street and NW 8th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 11/17/2026 and be completed by approximately 11/20/2026 (+/- 4 business days).

 

Work Zone #2

NE 6th Street and NE 8th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 11/30/2026 and be completed by approximately 12/03/2026 (+/- 4 days).

 

Work Zone #3

NW 7th Street and NW 9th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 12/04/2026 and be completed by approximately 12/09/2026 (+/- 4 business days).

 

Work Zone #4

NE 7th Street and NE 9th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 12/09/2026 and be completed by approximately 12/14/2026 (+/- 4 business days).

 

Work Zone #5

NW 11th Street and Grove Way for installation of two (2) paver crosswalks.  Work is expected to begin around 12/15/2026 and be completed by approximately 12/18/2026 (+/- 4 business days).

 

Work Zone #6

NE 10th Street and NE12th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 1/4/2027 and be completed by approximately 1/7/2027 (+/- 3 business days).

 

Work Zone #7

NW 12th Street and NW15th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 1/8/2027 and be completed by approximately 1/13/2027 (+/- 4 business days).

 

Work Zone #8

NE 11th Street and NW13th Street for installation of two (2) paver crosswalks.  Work is expected to begin around 1/13/2027 and be completed by approximately 1/19/2026 (+/- 4 business days).

 

Work zones will be completed in sequential order and work will only begin in a zone after the previous zone is completed.  These detours will facilitate safe installation of crosswalks. Refer to attached Exhibit 1- N Swinton Ave Detour.

 

City and CEI staff intends to maintain the Contractor's approved schedule, however proposed dates are subject to change due to inclement weather, unforeseen site conditions or unanticipated project delays.

 

Other work under this project (pavement rehabilitation, sidewalks, lighting, landscaping, etc.) will occur separately using flaggers only.

 

Work is anticipated to begin around 11/17/2026 and the last side street is expected to be re-opened to traffic by 1/19/2027.

 

City Attorney Review:

N/A

 

Funding Source/Financial Impact:

All costs associated with these closures have already been accounted for within Agreement ITBC No. 2024-010 and have been encumbered via PO 2024-1386.

 

Timing of Request:

Timely approval is requested to avoid delays in project completion and ensure roadways are opened promptly.