TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: October 1, 2024
Title
ITEM(S) A1 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 603 ANDREWS AVE.
ITEM(S) A2 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 310 NE 1ST AVE.
ITEM(S) B1 - ACCEPTANCE OF AN UNDERGROUND EASEMENT BY CITY OF DELRAY BEACH
Body
Recommended Action:
Recommendation
Consideration of the following items:
Item A1 - Motion to approve and accept a Right-of-Way Dedication by the owners of
603 Andrews Ave.
Item A2 - Motion to approve and accept a Right-of-Way Dedication by the owners of
310 NE 1st Ave.
Item B1 - Motion to approve and accept an Underground Easement by the City of Delray Beach.
Body
Background:
Item A1
Consider acceptance of a Right-of-Way Dedication located at 603 Andrews Ave.
The owner(s) submitted a building permit application for the subject property. During the application process it was determined that in accordance with LDR 5.3.1 (A) the roadway has an ultimate Right-of-Way of 50 ft. That corresponds to a half-width of 25 ft. The current Right-of-Way half-width is 12.5 ft. As a result, a 7.5 ft. Right-of-Way dedication was requested to satisfy the requirement. It was also determined that in accordance with LDR Section 6.1.2(C)(2)(e) for the intersecting roadways, a 25’ radius Right-of-Way is required and was also requested.
There is no City cost now or in the future for these items.
Item A2
Consider acceptance of a Right-of-Way Dedication located at 310 NE 1st Ave.
The owner(s) submitted a building permit application for the subject property. During the application process it was determined that in accordance with LDR 5.3.1 (A) the roadway has an ultimate Right-of-Way of 50 ft. That corresponds to a half-width of 25 ft. The current Right-of-Way half-width is 20 ft. As a result, a 5 ft. Right-of-Way dedication was requested to satisfy the requirement. It was also determined that in accordance with LDR 5.3.1 (A) the alley in the rear of the property has an ultimate Right-of-Way of 20 ft. That corresponds to a half-width of 10 ft. The current Right-of-Way half-width is 8 ft. As a result, a 2 ft. Right-of-Way dedication was requested.
There is no City cost now or in the future for these items.
Item B1
Consider acceptance of an Underground Easement located at intersection of NW 8th Ave and Enfield Rd.
FP&L requested an Easement the subject property. It was determined that an easement would be needed to allow access to utilities on this property. As a result, an easement agreement was created.
There is no City cost now or in the future for these items.
City Attorney Review:
Approved as to form and legal sufficiency.
Funding Source/Financial Impact:
N/A
Timing of Request:
The timing of these requests is of high importance to allow projects to continue construction.