File #: 23-1075    Version: 1 Name:
Type: Request Status: Passed
File created: 8/4/2023 In control: City Commission
On agenda: 9/5/2023 Final action: 9/5/2023
Title: APPROVAL OF AMENDMENT NO. 1 TO RFQ NO. 2021-005 WITH CHA CONSULTING INC., FORMALLY KNOWN AS A&P CONSULTING TRANSPORTATION ENGINEERS CORP. FOR ADDITIONAL CONSTRUCTION ENGINEERING AND INSPECTION SERVICES FOR THE RECLAIMED WATER MAIN AREA 10 PROJECT IN THE AMOUNT OF $18,464, FOR A REVISED CONTRACT VALUE OF $201,814.
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. Legal Review Checklist A & P Consulting Amendment, 3. Amendment No. 1 to 2021-005 Reclaimed Watermain Area 10, 4. Proposal for Amendment No. 1 to RFQ 2021-004, 5. Contract Increase to RFQ 2021-005, 6. Agreement - A&P Consulting Transportation Engineers Corp._Servic 052722

TO:                                          Mayor and Commissioners

FROM:                     Missie Barletto, Public Works Director

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     September 5, 2023

 

Title

APPROVAL OF AMENDMENT NO. 1 TO RFQ NO. 2021-005 WITH CHA CONSULTING INC., FORMALLY KNOWN AS A&P CONSULTING TRANSPORTATION ENGINEERS CORP. FOR ADDITIONAL CONSTRUCTION ENGINEERING AND INSPECTION SERVICES FOR THE RECLAIMED WATER MAIN AREA 10 PROJECT IN THE AMOUNT OF $18,464, FOR A REVISED CONTRACT VALUE OF $201,814.

 

Body

Recommended Action:

Recommendation

Motion to Approve Amendment No. 1 to RFQ 2021-005 with CHA Consulting Inc., formally known as A&P Consulting Transportation Engineers Corp. for additional Construction Engineering and Inspection (CEI) Services for the Reclaimed Water Main Area 10 Project (Project No. 17-133) in the amount of $18,464, for a revised contract value of $201,814.

 

Body

Background:

On April 6, 2021, City Commission approved Resolution No. 54-21 with an Agreement to A&P Consulting Transportation Engineers Corp. for Construction, Engineering, and Inspection (CEI) Services for the Reclaimed Water Main Area 10 Project pursuant to RFQ No. 2021-005 in an amount of $124,022.

 

The construction project had an initial contract time of 180 calendar days after the Notice to Proceed.  The Agreement terms will be from the date of full execution through the completion of work and full acceptance by the City.

 

In May 2022, DBE Management, Inc. dba DBE Utility Services (General Contractor), requested and received an extension in their construction completion time for an additional 426 calendar days due to material shortages resulting from the COVID-19 Pandemic. Continual CEI services needed to be extended accordingly and on June 24, 2022, a contract value increase of $59,328 was approved, for a revised contract value of $183,350.

 

Presently, additional CEI services are required to cover the final construction items necessary to close the project.

 

Attachments:

1.                     Legal Review Checklist - Amendment No. 1 to RFQ 2021-005

2.                     Amendment No. 1 to RFQ 2021-005

3.                     Proposal for Amendment No. 1 to RFQ 2021-005

4.                     Contract Value Increase to RFQ 2021-005

5.                     RFQ 2021-005

6.   Assumption & Assignment

 

This motion is in accordance with the Code of Ordinances Section 36.02 Commission Approval Required.

 

City Attorney Review:

Approved as to form and legal sufficiency.

 

Funding Source:

Funding in an amount not to exceed $18,464 is available from account number 442-36-260-536.63-10.

 

Timing of Request:

Approving this agreement is time sensitive to maintain the budget and schedule commitments.