File #: 16-428    Version: 1 Name:
Type: Contract Status: Agenda Ready
File created: 4/14/2016 In control: City Commission
On agenda: 5/3/2016 Final action: 12/31/2023
Title: CONTRACT AWARD TO R.J. BEHAR & COMPANY, INC. FOR CONSTRUCTION ENGINEERING AND INSPECTION (CEI) SERVICES FOR THE N.E. 2ND AVENUE/SEACREST BOULEVARD BEAUTIFICATION PROJECT
Attachments: 1. FINAL AGREEMENT.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners

FROM:                     John Morgan, Environmental Services Director

THROUGH:                     Donald B. Cooper, City Manager

DATE:                     May 3, 2016

 

Title

CONTRACT AWARD TO R.J. BEHAR & COMPANY, INC. FOR CONSTRUCTION ENGINEERING AND INSPECTION (CEI) SERVICES FOR THE N.E. 2ND AVENUE/SEACREST BOULEVARD BEAUTIFICATION PROJECT

Body

Recommended Action:

Recommendation

Motion to Approve a General Consulting Services Agreement with R.J. Behar & Company, Inc. for Construction Engineering and Inspection Services (CEI) for the NE 2nd Avenue / Seacrest Boulevard Beautification Project in the amount of $191,567.00.  (Project No. 11-067).

Body

Background:

In March of 2015 the City and Florida Department of Transportation (FDOT) entered into a Local Agency Program (LAP) Agreement in the amount of $1,209,570 for the construction phase of the NE 2nd Avenue / Seacrest Boulevard Beautification Project. Federal funds were made available to FDOT by the Federal Highway Administration for Construction Engineering and Inspection ($64,108.00) and construction ($534,232.00). On February 2, 2016, a LAP supplemental agreement providing an additional $100,000 from FDOT for construction was approved by City Commisison.  Additional funding was provided by the Community Redevelopment Agency (CRA) in the amount of $1,300,000.00 per the CRA/City Interlocal Agreement with the remaining funding for the project to be provided by the City.

 

On November 24, 2015, a Request for Qualifications was advertised for CEI Services for the NE 2nd Avenue / Seacrest Boulevard Beautification Project (RFQ No. 2016-022). These services are required by the FDOT for all LAP funded projects. Four firms responded with proposals and a selection committee ranked the proposals on January 28, 2016. The selection committee unanimously agreed that R.J. Behar & Company, Inc. was the top ranked respondent for RFQ No. 2016-022. Calvin, Giordano and Associates, Inc. (CGA) was ranked #2.  Amec Foster Wheeler Environment & Infrastructure, Inc. and AE Engineering, Inc. received the same ranking score, thus tied for #3.  On March 1, 2016, City Commission authorized City Staff to enter into contract negotiations with the top ranked firm, R.J. Behar & Company, Inc. Negotiations regarding the professional service hours relating to the scope of services were finalized at a Sunshine meeting held on April 18, 2016.

 

NE 2nd Avenue is considered to be an Off-System roadway, but FDOT requires that the project be constructed using the Big 4 (FDOT) Specifications.  This agreement includes full construction administration, testing and sampling, material certifications, final materials acceptance by FDOT, partial contract compliance/EEO, mandatory FDOT Construction and Administrative Compliance Audits, document scanning on LAPIT, and a full Final Estimates Closeout Package.

 

FDOT budgets 10% to 15% for CEI Services on their FDOT specification projects (which this project is considered to be) and this service authorization is for 10.3% of the overall construction cost.

 

The recommendation for award complies with the Code of Ordinances, Chapter 36, Section 36.02(C)(3) “Professional Services”.

 

City Attorney Review:

City Attorney recommends approval.

 

Finance Department Review:

Finance recommends approval.

 

Funding Source:

Funding is available upon budget transfer as follows:

    

334-3162-541-68.78         (General Construction Fund: NE 2 Ave/Seacrest Beaut.)                                          $136,067.00 (CRA/FDOT)

448-5461-538.68-78         (Stormwater Utility Fund: NE 2 Ave/Seacrest Beaut.)                                          $55,500.00 upon budget transfer from 448-5461-538-68.60

 

Timing of Request:

Construction for this project is ready to begin. It is necessary to have the CEI Services provider under contract prior to beginning construction.