File #: 24-1666    Version: 1 Name:
Type: Request Status: Passed
File created: 12/2/2024 In control: City Commission
On agenda: 1/7/2025 Final action: 1/7/2025
Title: APPROVAL OF AN ADDITIONAL SPENDING REQUEST TO AGREEMENT RFQ 2019-051 WITH BAXTER & WOODMAN, INC. FOR ADDITIONAL CONSTRUCTION, ENGINEERING, AND INSPECTION SERVICES (CEI) FOR THE OSCEOLA PARK NEIGHBORHOOD IMPROVEMENT PROJECT IN THE AMOUNT OF $62,000 FOR A REVISED TOTAL OF $1,407,865
Sponsors: Public Works Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. Proposal - Additional Spending Request, 3. Amend No. 3 to RFQ 2019-051, 4. Amend. No. 2 to RFQ 2019-051, 5. Amend. No. 1 to RFQ 2019-051, 6. RFQ 2019-051

TO:                                          Mayor and Commissioners

FROM:                     Missie Barletto, Public Works Director

THROUGH:                     Terrence R. Moore, City Manager

DATE:                     January 7, 2025

                    

Title

APPROVAL OF AN ADDITIONAL SPENDING REQUEST TO AGREEMENT RFQ 2019-051 WITH BAXTER & WOODMAN, INC. FOR ADDITIONAL CONSTRUCTION, ENGINEERING, AND INSPECTION SERVICES (CEI) FOR THE OSCEOLA PARK NEIGHBORHOOD IMPROVEMENT PROJECT IN THE AMOUNT OF $62,000 FOR A REVISED TOTAL OF $1,407,865

Body

Recommended Action:

Recommendation

Motion to Approve an Additional Spending Request to Agreement RFQ 2019-051 with Baxter & Woodman, Inc. for Additional Construction, Engineering, and Inspection Services (CEI) for the Osceola Park Project, in the amount of $62,000 for a revised total of $1,407,865.

 

Body

Background:

On March 3, 2020, City Commission (City) approved Resolution No. 40-20 to award an agreement to Baxter & Woodman, Inc. (BWI) for Professional Construction, Engineering, and Inspection Services (CEI) for Phase 1 of the Osceola Park Neighborhood Improvement Project (P/N. 16-095) in the amount of $495,953.

On January 5, 2021, the City approved Amendment No. 1 to the agreement in the amount of $487,912 to implement Phase II CEI Services for a revised total of $983,865.

On August 10, 2021, the City approved Amendment No. 2 to the agreement in the amount of $172,000 for additional CEI Services for Phase 1 due to construction delays, for a revised total of $1,115,865. 

On July 11, 2023, the City approved Amendment No. 3 to the agreement in the amount of $190,000 for additional CEI services due to delays caused by limited availability of construction materials, for a revised total of $1,345,865.

The Contractor is still working to supply all project close-out documents, which includes as-built drawings that are acceptable to the City.  Additional CEI services are needed to facilitate project close-out and approval of as-built drawings.

 This motion is in accordance with the City Code of Ordinances, Section 36.02 and City Policies and Procedures, Change Orders and Amendments.

Attachments:

1.                     Proposal for Additional Spending Request

2.                     Amendment No. 3

3.                     Amendment No. 2

4.                     Amendment No. 1

5.                     Agreement RFQ 2019-051

 

City Attorney Review:

Approved as to form and legal sufficiency.

 

Funding Source:

Funding will become available from 334-41-340-541.63-20 (Capital Outlay Osceola Pk. / Other Landscp. Beaut.) following a budget amendment, pursuant to approval of the FY24 CRA ILA for Constructions and Professional Services.

Timing of Request:

Approval of this amendment is time sensitive.