File #: 26-0245    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 2/18/2026 In control: City Commission
On agenda: 3/9/2026 Final action:
Title: ITEM(S) A1: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN BOBOLINK ROAD AND ALBATROSS ROAD AND ITEM(S) A2: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN CURLEW ROAD AND BOBOLINK ROAD
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. MOT Lindell Road Closure
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners                                   

FROM:                     Missie Barletto, Public Works Director

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     March 9, 2026

 

Title

ITEM(S) A1: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN BOBOLINK ROAD AND ALBATROSS ROAD AND ITEM(S) A2: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN CURLEW ROAD AND BOBOLINK ROAD

 

Body

Recommended Action:

Recommendation

Consideration of the following items:

 

Per LDR 7.1.8(C) (1)

Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2, 10-20-20)

Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2, 10-20-20)

 

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES

Item A1: Roadway Construction, LLC (Contractor) - As part of Agreement ITBC No. 2023-068 for the Lindell Boulevard Bicycle & Pedestrian Improvements Project (Public Works Project No. 17-074), a motion to approve and accept a Maintenance of Traffic Plan/Road Closure Plan for Lindell Boulevard (double speed table) Between Bobolink Road and Albatross Road (4-days).

 

Item A2: Roadway Construction, LLC (Contractor) - As part of Agreement ITBC No. 2023-068 for the Lindell Boulevard Bicycle & Pedestrian Improvements Project (Public Works Project No. 17-074), a motion to approve and accept a Maintenance of Traffic Plan/Road Closure Plan for Lindell Blvd. (single speed table) Between Curlew Road and Bobolink Road (2-days).

 

Body

Background:

 

MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE

To date, Contractor has utilized ten (10) roadway closure days, leaving four (4) allowable roadway closure days before City Commission approval is required. For the completion of the three (3) speed table reconstruction areas, Contractor is requesting a total of six (6) roadway closure days. Of these six (6) days, four (4) days fall within the remaining allowable closure days, and the remaining two (2) days would exceed the contractual allowance, requiring City Commission approval.

 

Item A1

Consider acceptance of a Maintenance of Traffic Plan/Road Closure Plan by Contractor to ensure the safety of construction crews and the public while milling and repaving Lindell Boulevard between Bobolink Road and Albatross Road. Residents will maintain access to their homes however temporary street parking may be necessary. The closure is anticipated to last approximately 4 days, beginning on or around March 23, 2026.

 

Item A2

Consider acceptance of a Maintenance of Traffic Plan/Road Closure Plan by Contractor to ensure the safety of construction crews and the public while milling and repaving Lindell Boulevard between Curlew Road and Bobolink Road. Residents will maintain access to their homes however temporary street parking may be necessary. The closure is anticipated to last approximately 2 days, beginning on or around March 30, 2026.

 

City Attorney Review:

N/A

 

Funding Source/Financial Impact:

N/A

 

Timing of Request:

The timing of this request is of high importance to allow the project to continue construction.