File #: 16-306    Version: 1 Name:
Type: Contract Status: Agenda Ready
File created: 3/11/2016 In control: City Commission
On agenda: 4/5/2016 Final action: 12/31/2023
Title: BID AWARD TO FOSTER MARINE CONTRACTORS, INC. FOR THE INSTALLATION OF SIDEWALKS ON SE 4TH STREET PROJECT (BID NO. 2016-059C)
Sponsors: Environmental Services Department
Attachments: 1. Bid Tab, 2. Location Map, 3. Interlocal Agreement with the CRA 2015 - 2016
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                  Mayor and Commissioners

FROM:            John Morgan, Director of Environmental Services

THROUGH:   Donald B. Cooper, City Manager

DATE:            April 5, 2016

 

Title

BID AWARD TO FOSTER MARINE CONTRACTORS, INC. FOR THE INSTALLATION OF SIDEWALKS ON SE 4TH STREET PROJECT (BID NO. 2016-059C)

Body

Recommended Action:

Recommendation

Motion to award Bid No. 2016-059C to Foster Marine Contractors, Inc. in the amount of $219,224 for the installation of sidewalks on SE 4th Street (Project No. 15-002).

 

Body

Background:

SE 4th Street is bordered by residential and commercial uses; and is close to the downtown area, linking the two important roadways, Swinton Avenue and SE 5th Avenue.  Portions of the sidewalk exist along SE 4th Street, however, there are gaps that currently prevent pedestrian connectivity.  The Community Redevelopment Agency (CRA) and the City of Delray Beach conducted various meetings to determine the most feasible areas within the CRA District to provide safe, functional, and accessible sidewalks for pedestrians. The purpose of this project is to provide sidewalks which meet the City’s established level of service for areas with high pedestrian traffic.  The City considered the following factors for the installation of sidewalks with in the CRA limits: 1) Installation of sidewalks on both side of the street, 2) installation of sidewalks and connectivity near schools and churches, and 3) installation of sidewalks by parks to accommodate safe pedestrian travel. 

 

The project improvements include the construction of 5’ wide concrete sidewalk, and swales on both sides of SE 4th Street from Swinton Avenue to SE 5th Avenue.

On February 4, 2016, the City issued Bid 2016-059C for the installation of sidewalks on SE 4th street (Project No. 15-002).  The City received three (3) responses on March 4, 2016. Foster Marine Contractors, Inc. submitted  the lowest responsive bid with the price of $219,224.

The bid award is in accordance with the Code of Ordinances, Chapter 36, Section 36.02(A) (1), and “Sealed Competitive Method.

 

City Attorney Review:

Approved as to form and legal sufficiency.

 

Finance Department Review:

Finance recommends approval.

 

Funding Source:

Funding is available from CRA in the amount of $229,540.11 Account No.334-3162-541-63.11 (Public Works/ Road and Street Facilities). Funding is provided by the Community Redevelopment Agency and the project is included in the approved CRA Interlocal Agreement for FY 2015 - 2106.