TO:                                           CRA Board of Commissioners

FROM:                       Lori Hayward, Finance and Operations Director

THROUGH:                      Renée Jadusingh, Esq., Executive Director

DATE:                      October 1, 2019

 

Title

CRA FINANCIAL REPORT - AUGUST 2019

 

Body

Recommended Action:

Recommendation

Receive and File.

 

Body

Background:

Attached are the August 2019 Financial Statements [1] Statement of Net Assets and [2] Statement of Activities with Budget vs. Actual (YTD). Below are highlights of significant activities that occurred during the month of August:

 

1.                     West Atlantic Redevelopment- Project Development/Implementation (G/L #5120) - Payments totaling $11,366 were made for the following:

                     John Ibarra & Associates, Inc.- Boundary and topographic survey- $6,900

                     PJMD Engineering, Inc.- Future Land Use Map and Rezoning traffic survey- $2,000

                     Hatcher Construction In-Kind Rent- $2,466

 

2.                     Downtown-DB-Master Plan-OSS Facility (G/L #5201) - A payment in the amount of $51,865 was made to the City of Delray Beach for the installation of electrical services.

 

3.                     Downtown-DB-Master Plan-Downtown Trolley (G/L #5230) - A third quarter payment in the amount of $51,151 was made to the City of Delray Beach for the trolley services.

 

4.                     SW Neighborhood Plan-Block 63 Alley (CIP) (G/L #5360) - A payment in the amount of $59,473 was made to the City of Delray Beach.

 

5.                     SW Neighborhood Plan- Alleys (CIP) (G/L #5361) - A payment in the amount of $63,581 was made to the City of Delray Beach.

 

6.                     Redevelopment Sites-Maintenance (G/L #6303) - Payments totaling $27,385 were made to the following:

                     Sod Unlimited, Inc. - $23,348

                     Raymond Graves & Sons Construction, Inc.- $2,075

                     Waste Management, Inc.- $1,293

                     Buckeye Plumbing - $331

                     Island Air Conditioning - $103

                     Miscellaneous - $235

 

7.                     Affordable/Workforce Housing Program-A-Guide Funding-DBCLT (G/L #6535) - A third quarter A-GUIDE payment in the amount of $65,388 was made to DBCLT.

8.                     Carver Square & Corey Isle Housing Construction (G/L #6621) - Payments totaling $18,973 were made to the following:

                     Brooks + Scarpa Architects, Inc. - $17,073

                     MacLaren Sign Co., LLC - $1,900

 

9.                     City Contractual Services- Planning, IT, and Parking Manager- (G/L #7331) - A third quarter payment in the amount of $27,500 was made to the City of Delray Beach.

 

10.                     City Contractual Services- Code Officer (NW/SW Neighborhoods)- (G/L #7332) - A third quarter payment in the amount of $16,415 was made to the City of Delray Beach for the position.

 

11.                     City Contractual Services- Housing Rehab Inspector- (G/L #7334) - A third quarter payment in the amount of $11,761 was made to the City of Delray Beach for the position. 

 

12.                     City Contractual Services- 7415Engineering Inspector- (G/L #7339) - A third quarter payment in the amount of $17,752 was made to the City of Delray Beach for the position. 

 

13.                     Community Resource Enhancement-A-Guide Funding (G/L #7376) - A-GUIDE payments totaling $306,250 were made for the following:

                     Arts Garage - $68,750

                     Delray Beach Chamber of Commerce - $18,750

                     Delray Beach Historical Society - $31,250

                     Old School Square - $187,500

 

14.                     Economic Development Initiative- Economic Development Incentives- (G/L #7415) - Payments  $25,705 were made to the following:

                     Center for Technology, Enterprise & Development, Inc- $16,250

                     Cloud Computing Concepts- $7,605

                     Library Meeting space- $1,850

 

15.                     Economic Development Initiative- Economic Development Marketing- (G/L #7425) - Payments  $15,429 were made to the following:

                     Treasure Coast Regional Planning Council- $6,450

                     DG Communication Group, Inc.- $4,660

                     Jitter Flix Video, LLC- $2,350

                     Miscellaneous- $1,969

 

16.                     Office Space-Maintenance (G/L #8307) - Payments totaling $61,342 were made to the following:

                     Hatcher Construction & Development, Inc. - $56,453

                     Cope Architect, Inc.- $2,499

                     Zimmerman Tree Service - $1,525

                     Global Cleaning Services- $1,020

                     Island Air Conditioning- $525

                     Sod Unlimited, Inc. - $500

                     Miscellaneous - $345

 

 

 

Attachment(s): Exhibit A - August 2019 Financial Statements