TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: November 17, 2026
Title
APPROVAL OF AMENDMENT NO. 1 TO AGREEMENT RFQ NO. 2025-006 WITH MAN CON, INC. TO ESTABLISH A GUARANTEED MAXIMUM PRICE (GMP) FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES FOR THE HISTORIC MARINE WAY SEAWALL, ROADWAY, UTILITY, AND DRAINAGE IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 17-047) IN THE AMOUNT OF $55,000,000.00 FOR A REVISED AGREEMENT TOTAL OF $55,409,005.00
Body
Recommended Action:
Recommendation
Motion to approve Amendment No. 1 to Agreement RFQ No. 2025-006 with Man-Con, Inc. to establish a GMP for Construction Manager at Risk (CMAR) Services for the Historic Marine Way Seawall, Roadway, Utility, and Drainage Improvements Project (Public Works Project No. 17-047), in the amount of $55,000,00.00 for a revised agreement total of $55,409,005.00.
Body
Background:
On March 11, 2025, the City Commission (City) approved Resolution No. 69-26 to award an agreement to Man-Con, Inc. for CMAR Services related to the Historic Marine Way Seawall, Roadway, Utility, and Drainage Improvements Project pursuant to RFQ No. 2025-006. The City intended to award two (2) separate phases for the CMAR services for the project. The first phase would be for Pre-Construction Services and is identified as Phase I. The second phase would be for Construction Services, if approved, and is identified as Phase II.
Marine Way, between Atlantic Avenue and SE 1st Street, has been experiencing flooding for at least the past 15 years. The proposed construction project includes: installing a new seawall with a higher cap elevation, adding a new underground master stormwater pump station, upsizing drainage pipes, replacing water and sewer infrastructure, beautifying the roadway area with a new shared-use paver road (near Deck 84), resident on-street parking, decorative street lighting, and other amenities along the...