File #: 24-12    Version: 1 Name:
Type: Request Status: Passed
File created: 12/15/2023 In control: City Commission
On agenda: 1/16/2024 Final action: 1/16/2024
Title: APPROVAL OF AMENDMENT NO. 1, UNDER REQUEST FOR QUALIFICATION (RFQ) NO. 2020-027, AND RESOLUTION NO. 150-21, WITH CHEN MOORE AND ASSOCIATES, INC., FOR ENGINEERING DESIGN SERVICES FOR FORCEMAIN LIFT STATION 50 TO SOUTH CENTRAL REGIONAL WASTEWATER TREATMENT PLANT IN A TOTAL AMOUNT NOT TO EXCEED $318,852.
Sponsors: Utilities Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. Legal Review Checklist Chen Moore Amendment No. 1.pdf, 3. Amendment No 1- FORCEMAIN Lift Station (LS50) to SCRWWTP.pdf, 4. Exhibit A Scope of Services for Phase II.pdf, 5. Exhibit B- Fee Summary.pdf, 6. Packet_for_Bid_RFQ_NO._2020-027, 7. Fully Executed Agreement - Chen Moore Associates Inc_
TO: Mayor and Commissioners
FROM: Hassan Hadjimiry, P.E., Utilities Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: January 16, 2024

Title
APPROVAL OF AMENDMENT NO. 1, UNDER REQUEST FOR QUALIFICATION (RFQ) NO. 2020-027, AND RESOLUTION NO. 150-21, WITH CHEN MOORE AND ASSOCIATES, INC., FOR ENGINEERING DESIGN SERVICES FOR FORCEMAIN LIFT STATION 50 TO SOUTH CENTRAL REGIONAL WASTEWATER TREATMENT PLANT IN A TOTAL AMOUNT NOT TO EXCEED $318,852.

Body
Recommended Action:
Recommendation
Motion to approve Amendment No. 1, under RFQ No. 2020-027 and Resolution No. 150-21, with Chen Moore and Associates, Inc., for Engineering Design Services for Forcemain 50 to South Central Regional Wastewater Treatment Plant in a total amount not to exceed $318,852.
Body
Background:
The City of Delray Beach owns and maintains a 20-inch force main from Lift Station 50 (LS 50) to the South Central Regional Wastewater Treatment Plant (SCRWWTP), approximately 2.5 miles in length. This force main is the single pipeline conveying all of the wastewater from the City of Delray Beach service area, to the SCRWWTP. Any flow disruption caused by a private party’s action or a naturally occurring pipe break has the potential to result in a major wastewater spill, affecting service to the Delray Beach Utilities customers and the environment. On October 19, 2021, the City Commission approved Chen Moore and Associates, Inc. under RFQ No. 2020-027 Phase 1 Initial Assessment and Conditions Engineering Report that provided an assessment condition report of the pipe, and best feasible route for installation of a new parallel force main. Phase 2 under RFQ No. 2020-027 consists of the final design for replacement. The total fee proposal of Phase 2 is $318,852 and will be paid based upon the firm’s proposed hourly rates and actual hours worked. The project is expected to be completed within 390 calendar days. Breakout fees for task are as follows:

TASK FEE
TASK 1 - FIELD INVESTIGATIONS ...