Legislation Details

File #: 26-1409    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 10/22/2026 In control: City Commission
On agenda: 11/17/2026 Final action:
Title: APPROVAL OF AMENDMENT NO. 1 TO AGREEMENT RFQ NO. 2025-013 WITH KIEWIT CORPORATION TO ESTABLISH A GUARANTEED MAXIMUM PRICE (GMP) FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES FOR THE NORTHWEST NEIGHBORHOOD IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 17-020) IN THE AMOUNT OF $112,973,126.00 FOR A REVISED AGREEMENT TOTAL OF $113,736,942.00
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. RFQ No. 2025-013_Amendment No. 1 - A133, 3. Modified Exhibit A.1, 4. Modified Exhibit A.2, 5. Modified Exhibit A.3, 6. Modified Exhibit D, 7. Modified Exhibit E, 8. Modified Exhibit H, 9. Modified Exhibit J, 10. Modified Exhibit K, 11. Modified Exhibit L, 12. Modified Exhibit M, 13. Modified Exhibit N, 14. RFQ No. 2025-013_Legal Review - Amendment No. 1, 15. Resolution No. 70-26, 16. RFQ No. 2025-013_Agreement - A133, 17. RFQ No. 2025-013_General Conditions - A201
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: November 17, 2026

Title
APPROVAL OF AMENDMENT NO. 1 TO AGREEMENT RFQ NO. 2025-013 WITH KIEWIT CORPORATION TO ESTABLISH A GUARANTEED MAXIMUM PRICE (GMP) FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES FOR THE NORTHWEST NEIGHBORHOOD IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 17-020) IN THE AMOUNT OF $112,973,126.00 FOR A REVISED AGREEMENT TOTAL OF $113,736,942.00

Body
Recommended Action:
Recommendation
Motion to Amendment No. 1 to Agreement RFQ No. 2025-012 with Kiewit Corporation to establish a GMP for Construction Manager at Risk (CMAR) Services for the Northwest Neighborhood Improvements Project (Public Works Project No. 17-020) in the amount of $112,973,126.00 for a revised agreement total of $113,736,942.00.

Body
Background:
On April 7, 2026, the City Commission (City) approved Resolution No. 70-26 to award an agreement to Kiewit Corporation for CMAR Services related to the NW Neighborhood Improvements Project pursuant to RFQ No. 2025-013. The City intended to award two (2) separate phases for the CMAR services for the project. The first phase would be for Pre-Construction Services and is identified as Phase I. The second phase would be for Construction Services, if approved, and is identified as Phase II.

The NW Neighborhood Improvements Project, funded entirely by the Community Redevelopment Agency (CRA), aims to improve roadways, pervious alleyways, sidewalks, swales, driveways, stormwater drainage systems, potable water mains, reclaimed water mains and sanitary sewer systems, while also implementing traffic calming measures and providing decorative street lighting, landscaping, and irrigation within the project area.

The project area is bordered by Lake Ida Road to the north, Swinton Avenue to the east, W. Atlantic Avenue to the south, and Interstate 95 to the west.

The City, at its sole discretion...

Click here for full text