File #: 24-1642    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 11/25/2024 In control: City Commission
On agenda: 12/17/2024 Final action:
Title: APPROVAL OF AMENDMENT NO. 1 TO RFQ NO. 2023-066 WITH CDM CONSTRUCTORS, INC., FOR ADDITIONAL ENGINEERING DESIGN SERVICES NEEDED FOR PHASE ONE (1) OF THE CITY OF DELRAY BEACH WATER TREATMENT PLANT PROGRESSIVE DESIGN BUILD PROJECT (PROJECT NO. 23-005U), IN AN INCREASE AMOUNT OF $800,000, FOR A REVISED TOTAL OF $15,782,309.
Sponsors: Utilities Department
Attachments: 1. Agenda Cover Report, 2. DBIA Agreement - CDM Constructors Inc. (RFQ 2023-066), 3. Packet_for_Bid_RFQ_2023-066 Advertised, 4. Amd #1 to RFQ 2023-066 Progressive Design Build Water Plant DBIA Agreements.doc, 5. Ex A to Amd #1 to RFQ 2023-066 Progressive Design Build Water Plant DBIA Agreements.pdf, 6. Legal Review Checklist Amd #1 to Water Treatment Plant Design Build - CDM Smith - DBIA 535 and 545.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Hassan Hadjimiry, P.E., Utilities Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: December 17, 2024

Title
APPROVAL OF AMENDMENT NO. 1 TO RFQ NO. 2023-066 WITH CDM CONSTRUCTORS, INC., FOR ADDITIONAL ENGINEERING DESIGN SERVICES NEEDED FOR PHASE ONE (1) OF THE CITY OF DELRAY BEACH WATER TREATMENT PLANT PROGRESSIVE DESIGN BUILD PROJECT (PROJECT NO. 23-005U), IN AN INCREASE AMOUNT OF $800,000, FOR A REVISED TOTAL OF $15,782,309.

Body
Recommended Action:
Recommendation
Motion to Approve Amendment No. 1 to RFQ No. 2023-066 with CDM Constructors, Inc. for additional engineering design services needed for Phase one (1) of the City of Delray Beach Water Treatment Plant Progressive Design Build Project (Project No. 23-005U), in an increase amount of $800,000 for a revised total of $15,782,309.

Body
Background:
On June 21, 2023 the City of Delray Beach (City) advertised Request for Qualification No. 2023-066 for the City of Delray Beach Water Treatment Plant Progressive Design Build Project. On November 7, 2023, through Resolution No. 220-23 Commission approved the recommendation to negotiate with the highest ranked qualified firm in that CDM Constructors, Inc., out of three (3) firms was ranked highest. On March 5, 2024 under Resolution No. 74-24, City Commission approved the City Manager to execute an agreement with CDM Constructors, Inc., for Phase One (1) of the City of Delray Beach Water Treatment Plant Progressive Design Build Project for a negotiated fee of $14,982,309.

The project scope has changed from a 14 million gallon day (MGD) membrane process train addition, to a full replacement of the existing lime softening facility with a building sized for 25 MGD and installed process capacity of 22 MGD. Since a blended flow is no longer considered and a full treatment change is being implemented, CDM will perform specialized field work and gather data from the distribution system for geochemical and water quality mo...

Click here for full text