Legislation Details

File #: 24-36    Version: 1 Name:
Type: Request Status: Passed
File created: 12/27/2023 In control: City Commission
On agenda: 1/16/2024 Final action: 1/16/2024
Title: APPROVAL FOR ADDITIONAL SPENDING ON P2023-019 WITH MUSCO SPORTS LIGHTING, LLC FOR SPORTS LIGHTING AND INSTALLATION IN THE AMOUNT OF $159,000 FOR A REVISED TOTAL OF $448,900
Sponsors: Parks & Recreation Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. Agreement - Musco Sports Lighting LLC, 3. RES No 12-23_Musco, 4. LegalReview_Musco_MSA, 5. 1819-2 Equip & Amenities Parks & Playgrounds, 6. Lighting_Quote 232854_musco, 7. Bid Renewal_Second renewal memorandum 1819-2_public, 8. Second Renewal Discount Spreadsheet

TO:                                   Mayor and Commissioners

FROM:                                          Samuel Metott, Director, Parks and Recreation

THROUGH:    Terrence R. Moore, ICMA-CM

DATE:                      January 16, 2024

 

Title

APPROVAL FOR ADDITIONAL SPENDING ON P2023-019 WITH MUSCO SPORTS LIGHTING, LLC FOR SPORTS LIGHTING AND INSTALLATION IN THE AMOUNT OF $159,000 FOR A REVISED TOTAL OF $448,900

 

Body

Recommended Action:

Recommendation

Motion to approve additional spending on existing  contract no. P2023-019 with Musco Sports Lighting, LLC. for Sports Lighting and Installation in the amount of $159,000.

 

Body

Background:

On January 17, 2023, the City Commission approved Resolution No. 12-23 to award Master Services Agreement P2023-019 with Musco Sports Lighting, LLC. in the amount of $289,000 for lighting replacement at the Delray Beach Tennis Center utilizing the Clay County, Florida Solicitation No. RFP 18/19-2. In January 2023 the stadium court lighting was replaced but more replacements are needed to maintain practice courts to ATP standards for professional play.

 

Per the original agreement with Match Point Inc., the City must provide lighting at a specific foot candle illumination according to ATP standards.

 

Revised Contract Value

Jan. 17, 2023 through May 27, 2024 = $448,900

 

 

 

This motion is in accordance with the Code of Ordinances Chapter 36, Commission Approval Required and City Policies and Procedures, Change Orders, and Amendments.

 

Attachments:

 1. Original Agreement

 2. Resolution No. 12-23

 3. Legal Review Checklist

 4. Clay County Agreement

 5. Clay County Solicitation No. RFP 18/19-2

 6. Lighting Quote

 7. Second Renewal

 8. Second renewal  Spreadsheet

 

 

City Attorney Review:

N/A

 

Funding Source/Financial Impact:

334-90-260-519.46-40; General Construction

 

Timing of Request:

This is time sensitive in order to have installed prior to the Delray Beach Open in February 2024