Title: APPROVAL OF A MAINTENANCE OF TRAFFIC PLAN / ROAD CLOSURE PLAN FOR THE INSTALLATION OF DECORATIVE CROSSWALKS ON SIDE STREETS ALONG NORTH SWINTON AVE FROM NE/NW 6TH STREET TO NE/NW 13TH STREET FOR THE N. SWINTON AVENUE ROADWAY & UNDERGROUND UTILITY IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 19-012)
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. MOT Plan - N. Swinton Avenue Roadway & Underground Utility Improvements (19-012)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: November 2, 2026

Title
APPROVAL OF A MAINTENANCE OF TRAFFIC PLAN / ROAD CLOSURE PLAN FOR THE INSTALLATION OF DECORATIVE CROSSWALKS ON SIDE STREETS ALONG NORTH SWINTON AVE FROM NE/NW 6TH STREET TO NE/NW 13TH STREET FOR THE N. SWINTON AVENUE ROADWAY & UNDERGROUND UTILITY IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 19-012)

Body
Recommended Action:
Recommendation
Motion to Approve a Maintenance of Traffic Plan / Road Closure Plan for the installation of decorative crosswalks on side streets from NE/NW 6th Street to NE/NW 13th Street pursuant to ITBC No. 2024-010 for the N. Swinton Ave Roadway & Underground Utility Improvements Project. Having exceeded the allowable 14 days throughout the course of construction, All County Paving is requesting a Maintenance of Traffic Plan pursuant to LDR 7.1.8:

(C) Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2 , 10-20-20)

(1) Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2 , 10-20-20)

Body
Background:
MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
All County Paving, the construction contractor for the N. Swinton Ave Roadway & Underground Utility Improvements Project, has submitted a MOT proposing the closure of side streets along N. Swinton Avenue in eight (8) w...

Click here for full text