TO: CRA Board of Commissioners
FROM: Cassidy Heitman, Legal Advisor
THROUGH: Renée A. Jadusingh, Esq., Executive Director
DATE: October 27, 2026
Title
INTERLOCAL AGREEMENT BETWEEN THE CITY OF DELRAY BEACH AND THE DELRAY BEACH COMMUNITY REDEVELOPMENT AGENCY FOR FUNDING CONSTRUCTION PROFESSIONAL SERVICES FOR FISCAL YEAR 2026-2027
Body
Recommended Action:
Recommendation
Approve the Interlocal Agreement between the City of Delray Beach and Delray Beach Community Redevelopment Agency for funding the Capital Improvement Projects within the CRA District for Fiscal Year 2026-2027, in substantially attached form.
Body
Background:
The implementation of many projects contained in the Community Redevelopment Plan, particularly the public infrastructure projects resulting from the adopted Neighborhood and Redevelopment Plans, requires a joint City of Delray Beach (City) and Community Redevelopment Agency (CRA) effort. The typical arrangement involves the CRA funding all or a portion of the project, and the City’s staff overseeing the bidding and construction processes.
Each year, the City and CRA enter into an interlocal agreement to formalize the CRA’s commitment to fund specific projects. CRA funds are transferred at the time that the contract is awarded, or service authorization is approved for each project. Fiscal Year 2026-2027 projects include the following:
Fiscal Year 2026-2027 Projects
CRA GL# City Project # Project Name CRA Funding
5661 Pompey Park Construction Project $14,340,492
5661a Pompey Park Pre-Con and Project Owners Rep $93,005
5661b Pompey Park Construction Project Concession Stand $300,000
5622 NW Neighborhood Infrastructure Improvement Project $11,964,367
5368 SW 8th Avenue Streetscape Improvements $5,540,000
5201 Implementation of Old School Square Master Plan $458,500
Attachment(s): Exhibit A - ILA for FY 2026-2027 for General Capital Improvement Project