Legislation Details

File #: 26-0815    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 6/23/2026 In control: City Commission
On agenda: 7/14/2026 Final action:
Title: ITEM A1: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE PLAN FOR THE INTERSECTION OF SW 8TH AVENUE AND SW 2ND STREET FOR THE SW 8TH AVENUE/SW 2ND STREET INTERSECTION IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 25-005)
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. MOT_WYNN & SONS
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto- Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: July 14, 2026

Title
ITEM A1: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE PLAN FOR THE INTERSECTION OF SW 8TH AVENUE AND SW 2ND STREET FOR THE SW 8TH AVENUE/SW 2ND STREET INTERSECTION IMPROVEMENTS PROJECT (PUBLIC WORKS PROJECT NO. 25-005)

Body
Recommended Action:
Recommendation
Consideration of the following item:
Per LDR 7.1.8(C) (1), Maintenance of Traffic (MOT) Plan - All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2, 10-20-20)
Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2, 10-20-20)

Having exceeded the allowable 14 days throughout the course of construction, the contractor is requesting a MOT plan for the following:

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
Item A1: Wynn & Sons Environmental Construction, Inc. - a MOT/Road Closure Plan for the intersection of SW 8th Street and SW 2nd Avenue.

Body
Background:

MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES

Item A1: Consider acceptance of a MOT Plan by Wynn & Sons Environmental Construction, Inc. to close the intersection of SW 8th Avenue and SW 2nd Street for approximately 6 to 8 weeks, weather permitting, to allow the demolition of the roundabout and installation of a new raised intersection. Construction is anticipated to being around mid-July.

Pursuant to LDR 7.1.8(C)(1), City Commission approval is required for closures exceeding 14 days.

City Attorney Review:
N/A

Funding Source/Financial Impact:
There is no City cost now or in the future for these ...