Attachments: 1. Downtown Delray Medical Centre-Staff Report, 2. "EXHIBIT A "- Original SPRAB Conditions of Approval, 3. Excerpt Minutes - December 9, 2015 SPRAB Meeting, 4. Site Aerials, 5. Downtown Delray Plans, 6. Downtown Delray Medical Center Zoning Map, 7. Downtown Delray Medical Center FLUM Map, 8. Letter From Applicant, 9. City Commission Board Order
TO: Mayor and Commissioners
FROM: Timothy Stillings, Planning, Zoning and Building Department
THROUGH: Donald B. Cooper, City Manager
DATE: February 16, 2016

Title
APPEAL OF SPRAB APPROVAL OF A CLASS V SITE PLAN EXTENSION REQUEST FOR DOWNTOWN DELRAY MEDICAL CENTER LOCATED AT 530 SE 6TH AVENUE (QUASI-JUDICIAL HEARING)

Body
Recommended Action:
Recommendation
Approve a 24 month extension (expiring December 11, 2017) of the Class V site plan, landscape plan and architectural elevation plan for Downtown Delray Medical Center, by adopting the findings of fact and law contained in the staff report, and finding that the request, and approval thereof, meets criteria set forth in Section 2.4.4(F)(1)&(3) and Section 3.1 of the Land Development Regulations, subject to the following conditions:

1. That the project will be responsible for providing continuous paved access (i.e. along the alley abutting the property) from the nearest paved street (SE 5th Avenue and SE 6th Avenue) in addition to the improvements on its side of the center line of right-of-way. Such improvements must be provided in coordination with the City Engineer. A note to this effect shall be included on the site plan.

2. That the applicant shall provide the full cost of a bus shelter in the amount of $11,000 prior to the issuance of a building permit.

3. That the re-plat of the property must be recorded prior to the issuance of a building permit.

4. That the perimeter construction fence shall be removed within 60 days of the approval of the extension request and that the installation of a construction fence occurs only upon the issuance of a building permit.

5. That the fence is screened. Staff recommends that a green mesh screening is utilized and wraps the existing fence.

Body
Background:

COMMISSION AND SPRAB ACTIONS
The item before the City Commission is an appeal of the SPRAB (Site Plan Review and Appearance Board) action on the Class V site pl...

Click here for full text