File #: 16-447    Version: 1 Name:
Type: Contract Status: Agenda Ready
File created: 4/21/2016 In control: City Commission
On agenda: 5/17/2016 Final action: 12/31/2023
Title: CONTRACT CLOSEOUT (CHANGE ORDER NO. 1/FINAL PAYMENT) WITH B&B UNDERGROUND CONTRACTORS INC. FOR THE ALLEN AVENUE DRAINAGE PROJECT (BID NO. 2015-46)
Sponsors: Environmental Services Department
Attachments: 1. Change Order No 1. Final
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:               Mayor and Commissioners

FROM:          John Morgan, Environmental Services Director

THROUGH:   Donald B. Cooper, City Manager

DATE:           May 17, 2016

 

Title

CONTRACT CLOSEOUT (CHANGE ORDER NO. 1/FINAL PAYMENT) WITH B&B UNDERGROUND CONTRACTORS INC. FOR THE ALLEN AVENUE DRAINAGE PROJECT (BID NO. 2015-46)

 

Body

Recommended Action:

Recommendation

Motion to approve Contract Closeout Change Order No. 1 to B&B Underground Contractors, Inc., in the net contract deductive amount of ($15,577.75) and approve a final payment, in the amount of $13,390.16, to B&B Underground Contractors, Inc., for completion of the Allen Avenue Drainage Improvements Project No. 2009-015.  

 

Body

Background:

On July 7, 2015, the City Commission approved a bid award (Bid No. 2015-46) in the amount of $81,278 B&B Underground Contractors, Inc., for the Allen Avenue Drainage Project #2009-015. Change Order No. 1 and final payment in the net contract deductive amount of ($15,577.75), includes plus and minus quantity adjustment and liquidates the residual from contingency allowances.  All changes for the project are itemized on the attached Schedule “A”.  The project is complete and accepted by the City and all closeout documentation has been received.

This Change Order No. 1 and Final Payment is in compliance with Code of Ordinances, Chapter 36, Section 36.06 (A)(2), "Change Orders, Within the Scope of Work". After final payment in the amount of $13,390.16 is made, residual funds, in the amount of ($15,577.75), will be liquidated from Purchase Order #705198 to funding Account #448-5461-538-68.55 (Stormwater Utility Fund).

City Attorney Review:

Approved as to form and legal sufficiency.

 

Finance Department Review:

Finance recommends approval.

 

Timing of Request:

This item is time sensitive; contractor cannot be paid final payment for completion of the project until approved by Commission and the final change order is fully executed.