TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: March 9, 2026
Title
ITEM(S) A1: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN BOBOLINK ROAD AND ALBATROSS ROAD AND ITEM(S) A2: CONSIDERATION OF A MAINTENANCE OF TRAFFIC PLAN/ROAD CLOSURE PLAN FOR LINDELL BOULEVARD BETWEEN CURLEW ROAD AND BOBOLINK ROAD
Body
Recommended Action:
Recommendation
Consideration of the following items:
Per LDR 7.1.8(C) (1)
Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2, 10-20-20)
Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2, 10-20-20)
MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
Item A1: Roadway Construction, LLC (Contractor) - As part of Agreement ITBC No. 2023-068 for the Lindell Boulevard Bicycle & Pedestrian Improvements Project (Public Works Project No. 17-074), a motion to approve and accept a Maintenance of Traffic Plan/Road Closure Plan for Lindell Boulevard (double speed table) Between Bobolink Road and Albatross Road (4-days).
Item A2: Roadway Construction, LLC (Contractor) - As part of Agreement ITBC No. 2023-068 for the Lindell Boulevard Bicycle & Pedestrian Improvements Project (Public Works Project No. 17-074), a motion to approve and accept a Maintenance of Traffic Plan/Road Closure Plan for Lindell Blvd. (single speed table) Between Curlew Road and Bobolink Road (2-days).
Body
Background:
MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE
To date, Contractor has utilized ten (10) roadway closur...