File #: 24-120 CRA    Version: 1 Name:
Type: CRA Board Action Status: Agenda Ready
File created: 10/21/2024 In control: Community Redevelopment Agency
On agenda: 10/29/2024 Final action:
Title: COMPLETION OF RESTAURANT BUILDOUT AT CRA OWNED PROPERTY LOCATED AT 182 NW 5TH AVENUE
Attachments: 1. Agenda Cover Report, 2. Exhibit A - Location Map, 3. Exhibit B - Sixth Amendment to the Commercial Lease Agreement with Jerk and Lime at Nicole’s House, 4. Exhibit C - Second Amendment to Site Development Assistance Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: CRA Board of Commissioners
FROM: Christine Tibbs, Assistant Director
THROUGH: Renée A. Jadusingh, Executive Director
DATE: October 29, 2024

Title
COMPLETION OF RESTAURANT BUILDOUT AT CRA OWNED PROPERTY LOCATED AT 182 NW 5TH AVENUE

Body
Recommended Action:
Recommendation
Approve expenditure of funds to complete a restaurant buildout at CRA Owned property located at 182 NW 5th Avenue within CRA sub-area #3.

Body
Background:
At the November 17, 2021, CRA Board Meeting, the CRA Board approved a Commercial Lease Agreement with Jerk and Lime at Nicole’s House, LLC (Nicole’s House) for the CRA-owned property located at 182 NW 5th Avenue - The Muse House within the West Settlers Historic District.

At the September 1, 2022, CRA Regular Board Meeting, the Board approved authorizing the Executive Director to consider and, if acceptable, to approve Site Development Assistance Funding Agreement and later ratify the Agreement at the next scheduled Board meeting. To avoid potential delays, the funding agreement application was processed for approval administratively and was later ratified at the January 24, 2023, CRA Board Meeting.

Work has commenced and is underway, however delays in obtaining the interior alteration permit have caused delays in the completion of construction. Additionally, extended lead times for commercial kitchen items have also affected the completion of construction.

As a result, Nicole’s House requested an extension to the Buildout Period for the existing Commercial Lease Agreement. As stipulated in the Lease Agreement, when the Buildout Period expires, the tenant shall begin paying the full Monthly Base Rent amount. Additionally, Nicole’s House requested an extension to the Site Development Assistance Funding Agreement to assist with the cost of the improvements including kitchen buildout, electrical, plumbing, ADA-compliance, and related permitting fees. Both the Buildout Period and the Funding Agreement were set to expire on Ja...

Click here for full text