File #: 24-858    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 6/13/2024 In control: City Commission
On agenda: 7/9/2024 Final action:
Title: APPROVAL FOR ADDITIONAL SPENDING ON AGREEMENT RFQ NO. 2020-020 WITH BAXTER & WOODMAN, INC. FOR CONSTRUCTION ENGINEERING AND INSPECTION SERVICES FOR THE LOWSON BOULEVARD/SW 10TH STREET FROM DOVER ROAD TO SOUTHEAST 5TH AVENUE (US-1/FEDERAL HIGHWAY) PROJECT IN THE AMOUNT OF $135,000 FOR A REVISED CONTRACT TOTAL OF $1,319,810.64
Sponsors: Public Works Department, Purchasing Department
Attachments: 1. RFQ 2023-020 CEI Lowson Blvd with Baxter & Woodman - Addtl Spending Proposal #3, 2. Agenda Cover Memo - Additional Spending #2 RFQ 2020-020, 3. Proposal #2 - Additional Spending to RFQ 2020-020, 4. Agenda Cover Memo - Additional Spending #1 RFQ 2020-020, 5. Proposal #1 - Additional Spending to RFQ 2020-020, 6. Fully Executed Agreement - Baxter Woodman for Construction Engineering Inspection Services, 7. Legal Review Checklist - RFQ 2020-020 with Baxter & Woodman for Lowsn Blvd, 8. Resolution No. 98-21, 9. RFQ 2023-020 CEI Lowson Blvd with Baxter & Woodman - Final Solicitation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: July 9, 2024

Title
APPROVAL FOR ADDITIONAL SPENDING ON AGREEMENT RFQ NO. 2020-020 WITH BAXTER & WOODMAN, INC. FOR CONSTRUCTION ENGINEERING AND INSPECTION SERVICES FOR THE LOWSON BOULEVARD/SW 10TH STREET FROM DOVER ROAD TO SOUTHEAST 5TH AVENUE (US-1/FEDERAL HIGHWAY) PROJECT IN THE AMOUNT OF $135,000 FOR A REVISED CONTRACT TOTAL OF $1,319,810.64

Body
Recommended Action:
Recommendation
Motion to approve additional spending on Agreement RFQ No. 2020-020 with Baxter and Woodman, Inc. for Construction Engineering and Inspection (CEI) Services for the Lowson Boulevard/SW 10th Street from Dover Road to Southeast 5th Avenue (US-1/Federal Highway) Project (Public Works Project No. 17-009) in the amount of $135,000 for a revised contract total of $1,319,810.64.

Body
Background:
On July 6, 2021, the City Commission (City) approved Resolution No. 98-21 with an Agreement to Baxter & Woodman, Inc. for Construction Engineering and Inspection Services (CEI) for the Lowson Boulevard/SW 10th Street from Dover Road to Southeast 5th Avenue ((US-1/Federal Highway) Project, pursuant to RFQ No. 2020-020 in an amount of $730,583.64.

On August 15, 2023, the City approved a request for additional spending in the amount of $319,227 for extended CEI services. Material shortages related to the COVID-19 pandemic and the extended time of award of the contract agreement to E&M Equipment, Corp. (General Contractor) resulted in an additional 145 calendar days for construction. FDOT LAP Grant (436896-1-58-01) requirements for this project require continual CEI services, therefore additional funding was approved to extend these services.

On February 20, 2024, the City approved an additional spending request to extend CEI services in the amount of $135,000 through the then estimated project completion date of March 2024.

Due to continued construction delays, an additional s...

Click here for full text