TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: September 3, 2024
Title
ITEM(S) A1 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 655 NW 4th ST.
ITEM(S) A2 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 701 NW 4th ST.
ITEM(S) A3 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 203 SW 2nd ST.
ITEM(S) A4 - ACCEPTANCE OF A RIGHT-OF-WAY DEDICATION BY 2023 NE 2nd AVE.
Body
Recommended Action:
Recommendation
Consideration of the following items:
Item A1 - Motion to approve and accept a Right-of-Way Dedication by the owners of 655 NW 4th St.
Item A2 - Motion to approve and accept a Right-of-Way Dedication by the owners of 701 NW 4th St.
Item A3 - Motion to approve and accept a Right-of-Way Dedication by the owners of 203 SW 2nd St.
Item A4 - Motion to approve and accept a Right-of-Way Dedication by the owners of 2023 NE 2nd Ave.
Body
Background:
Item A1
Consider acceptance of a Right-of-Way Dedication located at 655 NW 4th St.
During the design of the NW Neighborhood Improvements Project, it was determined that in accordance with LDR 5.3.1 (A), NW 4th St. has an ultimate Right-of-Way of 50 ft. That corresponds to a half-width of 25 ft. The current Right-of-Way half-width is 0 ft. As a result, a 25 ft. Right-of-Way dedication was requested from the property owner(s), Melinda and Derek Peacock, to satisfy the requirement.
There is no City cost now or in the future for these items.
Item A2
Consider acceptance of a Right-of-Way Dedication located at 701 NW 4th St.
During the design of the NW Neighborhood Improvements Project, it was determined that in accordance with LDR 5.3.1 (A), NW 4th St. has an ultimate Right-of-Way of 50 ft. That corresponds to a half-width of 25 ft. The current Right-of-Way half-width is 0 ft. As a result, a 25 ft. Right-of-Way dedication was requested from the property owner(s), Shirley Johnson, to satisfy the requirement.
There is no City cost now or in the fu...
Click here for full text