TO: Mayor and Commissioners
FROM: Missie Barletto- Public Works Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: September 3rd, 2024
Title
ITEM(S) A1, MAINTENANCE OF TRAFFIC PLAN/ ROAD CLOSURE PLAN FOR INTERSECTION OF SW 2nd St and SW 6th Ave.
Body
Recommended Action:
Recommendation
Consideration of the following items:
Per LDR 7.1(C) (1)
Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2
, 10-20-20)
Closures greater than 14 days throughout the course of construction, which eliminate travel lanes or change the flow of traffic must be approved by the City Commission. Street closures that do not exceed 14 days throughout the course of construction may be approved administratively. (Ord. No. 50-20, § 2 , 10-20-20)
Having exceeded the allowable 14 days throughout the course of construction the following Maintenance of Traffic plans are petitioning additional closures as follows:
MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
Item(S) A
Item A1 - Wynn & Sons - Motion to approve and accept a Maintenance of Traffic/ Road closure Plan for the intersection of SW 2nd St and SW 6th Ave.
Body
Background:
MAINTENANCE OF TRAFFIC PLAN/ ROAD & LANE CLOSURES
Item A1
Consider acceptance of a Maintenance of Traffic Plan by Wynn & Sons to close the intersection of SW 2nd St and SW 6th Ave for six weeks to allow the demolition of the roundabout and installation of a new raised intersection.
Per LDR 7.1(C) (1) Maintenance of Traffic (MOT) Plan. All construction parking and staging that involves travel lane, bike lane, or sidewalk closures shall submit a MOT Plan as follows: (Ord. No. 50-20, § 2
Click here for full text