File #: 25-1240    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 9/19/2025 In control: City Commission
On agenda: 10/14/2025 Final action:
Title: APPROVAL OF AMENDMENT NO. 5 TO EXTEND THE TERMS OF AGREEMENT NO. L2202 (POMPEY PARK IMPROVEMENT PROJECT) MADE BETWEEN THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND THE CITY OF DELRAY BEACH
Sponsors: Parks & Recreation Department
Attachments: 1. Agenda Cover Report, 2. Legal Review L2202 Amendment 5.pdf, 3. L2202.A5.Unsigned 9.18.2025.pdf, 4. L2202_A4_Continuation of Standard Grant_6.26.2025.pdf, 5. L2202_Amendment No. 3_FE.pdf, 6. L2202 Delray Beach Pompey Park Amendment 2_FE.pdf, 7. L2202_Amendment 1_FullyExecuted.pdf, 8. L2202 Delray Beach-Pompey Park_LLI-Fully Executed Agreement.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners

FROM:                     Samuel Metott, Director, Parks and Recreation

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     October 14, 2025

 

Title

APPROVAL OF AMENDMENT NO. 5 TO EXTEND THE TERMS OF AGREEMENT NO. L2202 (POMPEY PARK IMPROVEMENT PROJECT) MADE BETWEEN THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AND THE CITY OF DELRAY BEACH

 

Body

Recommended Action:

Recommendation

Motion to approve Amendment No. 4 to extend the grant project completion date to December 31, 2025 and the grant period to March 1, 2026.

 

Body

Background:

On November 8, 2022 the City entered into a grant agreement with the State of Florida Department of Environmental Protection (DEP) for upgrades to Pompey Park and Pool. On April 27, 2023, the agreement was extended to April 30, 2024 and entered into the agreement as Amendment No. 1. Amendment No. 2 was entered into the agreement on April 24, 2024. Amendment No. 3 was entered into the agreement on October 29, 2024 and on June 24, 2025 the City of Delray Beach and the Florida Department of Environmental Protection entered into a Continuation of Standard Grant Agreement which incorporated Amendment No. 4 to the agreement.

 

In order to complete the kitchen renovation and install the purchased equipment, the Department requires an extension to finalize the remaining project elements.

 

City Attorney Review:

Approved as to form and legal sufficiency.

 

Funding Source/Financial Impact:

334-72-736-572.63-90; Capital Outlay

 

Timing of Request:

This is time sensitive to ensure deadlines are met to secure reimbursement.