Title: Service Authorization No. 12-16.1 to Mathews Consulting Inc. for design services related to the Tropic Palms Water Main Replacement project Phase 2 (Project No. 15-022)
Attachments: 1. Tropic Palms WM Phase 2 - Amendment 1, 2. Tropic Palms WM PH 2 Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: John Morgan, Environmental Services Director
THROUGH: Chief Neal de Jesus, Interim City Manager
DATE: February 7, 2017

Title
Service Authorization No. 12-16.1 to Mathews Consulting Inc. for design services related to the Tropic Palms Water Main Replacement project Phase 2 (Project No. 15-022)


Body
Recommended Action:
Recommendation
Motion to Approve Service Authorization No. 12-16.1 with Mathews Consulting, Inc. in the amount not-to-exceed $35,280 for design services related to value engineering the Tropic Palms Water Main Replacement Project Phase 2, Project No. 15-022.

Body
Background:
The City utilizes the approved engineering consultants retained through RFQ No. 2012-06. The original agreement with the Consultants was executed in January 2012, and recently extended to June 2017.

On October 26, 2016 an Invitation to Bid for Construction (ITBC 2013-090) of the Tropic Palms Water Main Replacement Phase 2 was advertised. Two (2) bids were received in response to the solicitation. The bid price exceeded the City’s available budget funding for the project of $1,182,612. The lowest bid was $1,351,623.

Value engineering identified potential cost savings by designing the water main with an alternative routing, in the swale areas versus in the roadway when available. This could potentially provide a considerable reduction in construction costs from $400,000 to $600,000.

Staff requested the consultant, Mathews Consulting Inc., to provide a scope of services addressing the alternative design.

This recommendation complies with the City Code of Ordinances, Chapter 36, Section 36.02 (A)(2), "Requests for Proposals, Requests for Qualifications, Requests for Letters of Interest".

City Attorney Review:
Approved as to form and legal sufficiency.

Finance Department Review:
Finance recommends approval.

Funding Source:
Funding is available from account number 442-5178-536-68.97 (Water/Sewer Renewal and Replacement Fu...