File #: 17-704    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/22/2017 In control: City Commission
On agenda: 10/3/2017 Final action: 10/3/2017
Title: RESOLUTION NO. 70-17: LOCAL AGENCY PROGRAM AGREEMENT WITH THE FLORIDA DEPARTMENT OF TRANSPORTATION FOR THE NE 2ND AVENUE / SEACREST BEAUTIFICATION PHASE 2 (NE 13TH STREET TO NE 22ND STREET) PROJECT.
Sponsors: Environmental Services Department
Attachments: 1. LOCATION MAP, 2. Legal Review Checklist FDOT LAP NE 2nd ave, 3. LAP agt, 4. Exhibit A, 5. Exhibit B, 6. Exhibit C, 7. Exhibit E, 8. Exhibit F, 9. Exhibit 1, 10. Resolution 70-17 LAP Agt - FDOT
TO: Mayor and Commissioners
FROM: Caryn Gardner-Young, Assistant City Manager
THROUGH: Chief Neal de Jesus, Interim City Manager
DATE: October 3, 2017

Title
RESOLUTION NO. 70-17: LOCAL AGENCY PROGRAM AGREEMENT WITH THE FLORIDA DEPARTMENT OF TRANSPORTATION FOR THE NE 2ND AVENUE / SEACREST BEAUTIFICATION PHASE 2 (NE 13TH STREET TO NE 22ND STREET) PROJECT.

Body
Recommended Action:
Recommendation
Motion to adopt Resolution No. 70-17; and consider approval to execute the Local Agency Program (LAP) Agreement with the Florida Department of Transportation (FDOT) for the funding of the NE 2nd Avenue Beautification Phase 2 (Project No. 16-032).

Body
Background:
The Seacrest Beautification projects are federally funded through the FDOT Local Agency Program. The project evolved into four phases. Phase 0 limits are from NE 4th Street/Lake Ida to NE 8th Street / George Bush Boulevard and construction was completed December 2016. Phase 1 limits are from NE 8th Street/George Bush Boulevard to NE 13th Street and anticipated to commence construction in October 2017. Phase 2 limits are from NE 13th Street to NE 22nd Street; and Phase 3 limits are from NE 22nd Street to Gulf Stream Boulevard.

In March 2015, the Mayor executed Resolution No. 07-15 thereby entering into a LAP agreement with FDOT for the construction of Phase 0 (NE 4th Street to NE 8th Street). In January 2017, the Mayor executed Resolution No. 01-17 for Phase 1 (NE 8th to NE 13th Street). In April 2016, City of Delray Beach (City) City Commission gave approval to move forward with design of Phase 2 (NE 13th Street to NE 22nd Street) and includes the following improvements:

- Reduction in travel lanes from 12' to 10'
- Dedicated 5' bike lanes on both sides of the road
- Concrete 5' sidewalks on both sides of the road
- Brick paver crosswalks

Phase 2 LAP agreement explains FDOT's project participation (refer to Exhibit "A" for project description); it states the terms and conditions of FDOT's financia...