File #: 18-0137 CRA    Version: 1 Name:
Type: CRA Discussion Status: Agenda Ready
File created: 10/3/2018 In control: Community Redevelopment Agency
On agenda: 10/9/2018 Final action:
Title: UPDATE - FY 2018-19 CRA WORK PLAN IMPLEMENTATION
Attachments: 1. Agenda Cover Report, 2. Exhibit A - CRA-Budget-Work Plan FY18-19
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           CRA Board of Commissioners

FROM:                       Jeff Costello, CRA Executive Director

DATE:                      October 9, 2018

 

Title 

UPDATE - FY 2018-19 CRA WORK PLAN IMPLEMENTATION

Body

 

Background:

 

Subsequent to the CRA Board’s adoption of the FY 2018-19 CRA Work Plan and Budget, CRA and City staff met to discuss implementation of the Capital Improvement Program Projects (“CIP”) for this fiscal year.  The City’s CIP Projects within the CRA District are managed by City Staff and funded partially or completely by CRA TIF funds.  In this instance, the CRA agreed to assist with managing certain CIP projects to facilitate the implementation of projects this fiscal year.  The following is a breakdown of the projects that will be managed by City or CRA.

 

Capital Improvement Projects

Management

Phase

Project Name

CRA Funding

CRA

Construction

NW 5th Avenue Alleys

$740,000

CRA

Construction

SW Neighborhood Alleys

$930,000

CRA

Construction

Block 63 Alley

$265,000

CRA

Design & Implementation

Wayfinding Signage

$400,000

CRA

Construction

NE 3rd Street/Avenue/Alley Improvements

$2,000,000

CRA

Design

Old School Square Master Plan

$500,000

City

Construction

OSS Campus/Park Improvements

$200,000

City

Design

Swinton/Atlantic Intersection

$500,000

City

Design

Swinton Avenue Complete Street

$200,000

City

Construction

SW 3rd Ct/SW 4th St/SW 6th St/SW 7th Ave/Alleys Improvements (SW Neighborhood)

$6,888,200

City

Construction

Meritt Park Playground-Poured-in-Place Surfacing

$200,000

City

Construction

Osceola Park Neighborhood Improvements

$1,000,000

City

Design

NW Neighborhood Improvements

$1,000,000

City

Design

Pompey Park Master Plan

$550,000

City

Construction

Hilltopper Stadium Restroom/Concession Bldg.

$600,000

TOTAL

 

 

$15,973,200

 

CRA Projects

 

1.                     Rehabilitation of 98 NW 5th Avenue (Design only) - Work Assignment anticipated for Board consideration anticipated on 11-13-18.

2.                     Development of commercial building at 95 SW 5th Avenue (Design only) - Work Assignment anticipated for Board consideration anticipated on 11-13-18.

3.                     Carver Square - Construction of 20 Single Family Homes for low to moderate income families - Conceptual Design Phase - Redesign based on CRA Board’s direction on 9-11-18.

4.                     Carver Isle - Construction of 10 Single Family Homes for low to moderate income families - Design Development Phase of the project (Construction Drawings)

5.                     Arts Warehouse - Renovations to backroom

6.                     Re-surfacing Block 60 parking lot

Bids

7.                     RFP - SW 600-800 Blocks of W. Atlantic Avenue

a.                     Issue Date: August 21, 2018

b.                     Submittal Date: November 2, 2018 at 2:00 p.m.

8.                     RFB - 20 Swinton Avenue - CRA Office Renovation

a.                     Issue Date: October 8, 2018

b.                     Submittal Date: November 7, 2018 at 2:00 p.m.

9.                     RFB - NW/SW Neighborhood Signs - Conceptual designs to be presented to the CRA Board on 11-13-18

a.                     Issue Date: TBD

Attachment(s): Exhibit A - FY 2018-19 CRA Work Plan

 

CRA Attorney Review:

N/A

 

Finance Review:

N/A

 

Funding Source/Financial Impact:

N/A

 

Timing of Request:

N/A