File #: 20-1022    Version: 1 Name:
Type: Request Status: Passed
File created: 11/30/2020 In control: City Commission
On agenda: 1/5/2021 Final action: 1/5/2021
Title: APPROVAL OF AMENDMENT NO. 1 TO BAXTER & WOODMAN, INC. FOR CONSTRUCTION, ENGINEERING, AND INSPECTION SERVICES (CEI) FOR THE OSCEOLA PARK NEIGHBORHOOD IMPROVEMENT PROJECT IN THE AMOUNT OF $487,912 (PROJECT NO. 16-095).
Sponsors: Public Works Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. Amendment 001, 3. Amendment 1 Exhibit A, 4. Amendment 1 Exhibit B, 5. Legal Review Checklist Amendment 1 to Osceola Park (1), 6. Agenda Cover Report CEI Osceola, 7. 2019-051 CEI Services for Osceola Park Neighborhood Improvements - FINAL
TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Jennifer Alvarez, City Manager
DATE: January 5, 2021


Title
APPROVAL OF AMENDMENT NO. 1 TO BAXTER & WOODMAN, INC. FOR CONSTRUCTION, ENGINEERING, AND INSPECTION SERVICES (CEI) FOR THE OSCEOLA PARK NEIGHBORHOOD IMPROVEMENT PROJECT IN THE AMOUNT OF $487,912 (PROJECT NO. 16-095).
Body
Recommended Action:
Recommendation
Motion to Approve Amendment No. 1 to the Agreement with Baxter & Woodman, Inc. for Construction, Engineering, and Inspection Services (CEI) for the Osceola Park Project, in the amount of $487,912, for a total contract amount not to exceed $983,865.

Body
Background:
On March 3, 2020, City Commission approved Resolution No. 40-20 to Baxter & Woodman, Inc. (BWI) for Professional Construction, Engineering and Inspection Services (CEI) for the construction of the Osceola Park Neighborhood Improvement Project (Phase I) in the amount of $495,953.
The original solicitation RFQ No. 2019-051 provided that if determined to be in the City’s best interest and, based upon BWI’s performance in Phase I, the City may renew the Agreement for an additional one (1) year for Phase II services. The City has determined that it is in its best interests to amend the Agreement to include Phase II services that will provide improvements to the infrastructure and safety of the neighborhood, including water, sewer, reclaimed water, drainage, sidewalks and street lighting. The general project limits are from SE 4th Street to SE 10th Street and from Swinton Avenue to Federal Highway.
This motion is in accordance with the City Code of Ordinances, Section 36 and City Policies and Procedures, Change Orders and Amendments.
Attachments:
Legal Review Checklist
Amendment No. 1 + Exhibits A & B
March 3, 2020 Agenda Cover Memo
Advertised RFQ No. 2019-051

City Attorney Review:
Approved as to form and legal sufficiency.

Funding Source:
Funding is available from 334-41-340-541....