File #: 21-926    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 8/13/2021 In control: City Commission
On agenda: 9/13/2021 Final action:
Title: APPROVAL OF RESOLUTION NO. 129-21 TO APPROVE AN AGREEMENT WITH CUSTOM BUILT MARINE CONSTRUCTION, INC. FOR THE CONSTRUCTION OF ISLAND DRIVE BRIDGE REHABILITATION PROJECT PURSUANT TO ITBC NO. 2021-035 (PROJECT NO. 19-014) - $1,226,578
Sponsors: Public Works Department, Purchasing Department
Attachments: 1. Agenda Cover Report, 2. ITBC 2021-035 Agreement, 3. Legal Review Checklist Custom Built Marine Island Drive Bridge Rehab, 4. Reso. 129-21 - Custom Built Marine, 5. Custom Built Marine Submittal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                          Mayor and Commissioners

FROM:                     Missie Barletto, Public Works Director

THROUGH:                     Terrence R. Moore, ICMA-CM

DATE:                     September 13, 2021

 

Title

APPROVAL OF RESOLUTION NO. 129-21 TO APPROVE AN AGREEMENT WITH CUSTOM BUILT MARINE CONSTRUCTION, INC. FOR THE CONSTRUCTION OF ISLAND DRIVE BRIDGE REHABILITATION PROJECT PURSUANT TO ITBC NO. 2021-035 (PROJECT NO. 19-014) - $1,226,578

 

Body

Recommended Action:

Recommendation

Motion to Approve Resolution No. 129-21 to award an Agreement with Custom Built Marine Construction, Inc. for the construction of Island Drive Bridge Rehabilitation Project pursuant to ITBC No. 2021-035 (Project No. 19-014).

 

Body

Background:

The City of Delray Beach (City) Public Works Department has identified the need to structurally repair the sub-structure and pilings to the Island Drive Bridge due to saltwater deterioration from the Intracoastal Waterway. The bridge is located approximately 0.03 miles west of Andrews Avenue, and it carries local traffic and pedestrians on Island Drive over the canal. The bridge was built in 1960 and later reconstructed in 1979. The structure is owned and maintained by the City.

 

The scope of work includes the construction of a new seawall at the northwest corner of the bridge, concrete repairs to the bridge superstructure and substructure, installation of cathodic galvanic pile jackets around each pile, the removal of all overgrown vegetation, and general roadway and drainage improvements.

 

The City issued Invitation to Bid Construction (ITBC) No. 2021-035 to acquire a firm which will provide all labor, materials, tools, equipment, supplies and supervision related to the construction of the Island Drive Bridge Rehabilitation project.

 

On June 25, 2021, the City received two (2) submittals pursuant to ITBC No. 2021-035. The low bid submitted by Custom Build Marine Construction, Inc. was deemed responsive and responsible to the Bid requirements.

 

Name of Bidder                                                                                    Total Bid Amount

Custom Built Marine Construction, Inc.                     $1,226,577.50

Interstate Construction, LLC.                                          $1,523,443,69

 

Therefore, staff recommends award of the Bid to Custom Built Marine Construction, Inc. in the total bid price of $1,226,577.50. Construction is expected to be substantially completed within 210 days from the date of the City’s Notice to Proceed, barring typical construction delays, such as those forced by inclement weather and COVID-19, and completed and ready for final payment no later than 30 days after substantial completion is accepted by the City.

 

This motion is in accordance with Code of Ordinances Section 36.02 Commission Approval Required.

 

Attachments:

 

1.                     2021-035 Agreement

2.                     Resolution No. 129-21

3.                     Legal Review Checklist

4.                     Custom Built Marine Construction bid submittal

 

City Attorney Review:

The City Attorney approves as to form as legal sufficiency.

 

Funding Source:

Account No. 377-41-340-541.63-04 (Island Drive Bridge Maintenance) - $1,176,577.50

Account No. 441-36-300-536.68-43 (Island Drive Bridge Maintenance) - $50,000.00

 

Timing of Request:

Approving this agreement is time sensitive in order to maintain the project timeline.