File #: 22-648    Version: 1 Name:
Type: Request Status: Agenda Ready
File created: 5/13/2022 In control: City Commission
On agenda: 6/14/2022 Final action:
Title: MOTION TO APPROVE EXPENDITURE OF FUNDS IN AN AMOUNT NOT TO EXCEED $1,178,505 IN ACCORDANCE WITH AN APPROVED AGREEMENT WITH GULF BUILDING, LLC. FOR PROFESSIONAL DESIGN-BUILD ENGINEERING SERVICES FOR (PHASE I) FIRE STATION 113 PURSUANT TO RFP NO. 2019-008
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. 256197_Phase 1 Acceptance_051222, 3. Gulf Building_FS 113_Phase I Proposal Revised, 4. Agreement - Gulf Building, LLC. (Fire Station 113 Design Build Agreement), 5. Resolution 161-19
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto, Director Public Works
THROUGH: Terrence R. Moore, ICMA-CM
DATE: June 14, 2022

Title
MOTION TO APPROVE EXPENDITURE OF FUNDS IN AN AMOUNT NOT TO EXCEED $1,178,505 IN ACCORDANCE WITH AN APPROVED AGREEMENT WITH GULF BUILDING, LLC. FOR PROFESSIONAL DESIGN-BUILD ENGINEERING SERVICES FOR (PHASE I) FIRE STATION 113 PURSUANT TO RFP NO. 2019-008

Body
Recommended Action:
Recommendation
Motion to approve the expenditure of funds in an amount not to exceed $1,178,505 in accordance with an approved agreement with Gulf Building LLC. for Design-Build Engineering Services for (Phase 1) Fire Station 113 pursuant to RFP No. 2019-008 (Project No. 16-012).

Body
Background:
On November 28, 2018, the City of Delray Beach (City) issued a Request for Proposal (RFP) for Fire Station 113 (FS113). The project goal was for the selected firm to complete the design, develop plans and specifications, and construct the fire station using the guaranteed maximum price contract model. On April 5, 2022, Commission approved the overall contract agreement with Gulf Building LLC.

Following a number of negotiation meetings with Gulf Building LLC during which a not-to-exceed price was established, Staff is seeking Commission approval to expend funds in an amount not to exceed $1,178,505 to provide Phase 1 services for the completion of the engineering design and permitting tasks for this project.

The project goal for Phase 1 is for Gulf Building, LLC. to complete the design/engineering, develop plans and specifications, and submit the 60% guaranteed maximum construction price (GMP) for future Commission Approval. Once the GMP is received, the City may choose to: a) accept the contract sum and proceed with construction of the fire station (Phase 2), or b) enter into negotiations on the scope and contract sum, or c) reject the amendment and either cancel the project or proceed with another contractor to build the fire station.

The moti...

Click here for full text