TO:                                           CRA Board of Commissioners

FROM:                       Gina Clayton, Finance & Operations Director

THROUGH:                      Renée A. Jadusingh, Esq., Executive Director

DATE:                      May 24, 2022

 

Title

BUDGET AMENDMENT NO. 1, FISCAL YEAR 2022-2023

 

Body

 

Recommended Action:

Recommendation

Approve CRA Resolution No. 2023-02 adopting Budget Amendment No. 1 for FY 2022-2023.

 

Body

Background:

Attached please find Resolution No. 2023-02 Budget Amendment No. 1 - FY 2022-2023. The items highlighted in yellow are modifications that are being proposed in this amendment. The following are significant modifications included in the proposed amendment:

 

1.                     TIF- City revenue (G/L #4005) - A decrease of ($153,352) was a result of Palm Beach County Tax Appraiser’s property valuation dated 3/31/2023. 

 

2.                     TIF- County revenue (G/L #4010) - A decrease of ($206,707) was a result of Palm Beach County Tax Appraiser’s property valuation dated 3/31/2023.   

 

3.                     General Carryforward Fund (G/L#4500) - Based on an internal draft of the CRA Financials for FY 2021- 2022, it’s estimated that the CRA’s General Fund Balance as of September 30, 2022, will be $31,500,000. The budget line was increased by $1,498,352, and the final amount will be adjusted after the completion audit. 

 

4.                     Other Income (G/L#4600) - Pulte Homes provided the CRA with a participation fee (revenue) for the homes Pulte Homes sold at the Carver Square Neighborhood totaling $195,773.

 

5.                     West Atlantic Redevelopment /West Atlantic Master Plan- NW 800 Block Redevelopment (G/L #5124) - The budget line was increased by $1,000,000. The cost estimate for this project from our consultant was approximately $6,000,000. We are setting aside additional funds to reach the cost estimate in order to start this project.

 

6.                     Osceola Park Neighborhood (CIP) (G/L#5510) - The City of Delray Beach Public Works Department requested additional funds for this project. The additional funds of $257,971 will be utilized for construction as follows:

-$190,000 in Osceola Park Neighborhood Project Phase II Construction Engineering Services

-$67,971.43 in Osceola Park Neighborhood Project Phase I and II for Construction Services

 

 

 

 

 

Attachment(s): Exhibit A - Resolution No. 2023-02 - Budget Amendment No. 1 FY 2022-2023; Exhibit B - FY 2022-2023 Budget Amendment No. 1

 

CRA Attorney Review:

N/A

 

Finance Review:

Prepared and reviewed by Executive Director and Finance & Operations Director.

 

Funding Source/Financial Impact: