Title: UTILITY WORK BY HIGHWAY CONTRACTOR AGREEMENT WITH FLORIDA DEPARTMENT OF TRANSPORTATION FOR CONSTRUCTION OF UTILITY RELOCATIONS RELATED TO FLORIDA DEPARTMENT OF TRANSPORTATION'S I-95 AT STATE ROAD 806 / ATLANTIC AVENUE INTERCHANGE ENHANCEMENT PROJECT (CITY PROJECT NO. 14-075).
Sponsors: Environmental Services Department
Attachments: 1. Utility Work by Highway Contractor Agreement (FDOT), 2. Legal Review Checklist FDOT Utility Work Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Marjorie G. Craig, P.E., Utilities Director
THROUGH: Chief Neal de Jesus, Interim City Manager
DATE: September 7, 2017

Title
UTILITY WORK BY HIGHWAY CONTRACTOR AGREEMENT WITH FLORIDA DEPARTMENT OF TRANSPORTATION FOR CONSTRUCTION OF UTILITY RELOCATIONS RELATED TO FLORIDA DEPARTMENT OF TRANSPORTATION'S I-95 AT STATE ROAD 806 / ATLANTIC AVENUE INTERCHANGE ENHANCEMENT PROJECT (CITY PROJECT NO. 14-075).

Body
Recommended Action:
Recommendation
Motion to Approve a Utility Work by Highway Contractor Agreement with the Florida Department of Transportation for performing construction services relocating water utilities relating to the Florida Department of Transportation's (FDOT) I-95 at State Road 806 / Atlantic Avenue Interchange enhancements project, FDOT Financial Project ID No. 434722-1-56-02 (City Project No. 2014-075).

Body
Background:
The proposed roadway enhancements for the I-95 and Atlantic Avenue intersection are in the final design phase by FDOT, which includes the addition of turn lanes and re-alignments of on/off ramps. The project limits along Atlantic Avenue corridor extend from the E-4 Canal (east side of Atlantic Community High School) to NW 10th Avenue.

To accommodate the enhancements, water mains that are currently in FDOT’s Right-of-Way within the footprint of the proposed improvements will need to be relocated and/or adjusted. At approximately two dozen areas along the corridor, existing water mains have been identified to conflict with the proposed improvements. The City’s consultant, Kimley Horn Associates, will be submitting final utility relocation plans and specifications to the FDOT’s design consultant for incorporation into FDOT’s highway construction documents, to be bid and constructed with the roadway enhancements.

The attached “Utility Work by Highway Contractor Agreement” between the FDOT and the City of Delray Beach will allow the FDOT to have their contractor perform the utility relocati...

Click here for full text