File #: 20-813    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 9/29/2020 In control: City Commission
On agenda: 11/17/2020 Final action:
Title: RESOLUTION NO.167-20: REQUESTING APPROVAL OF AN INTERLOCAL AGREEMENT (ILA) BETWEEN PALM BEACH COUNTY AND THE CITY OF DELRAY BEACH FOR THE DESIGN AND CONSTRUCTION OF A TRAFFIC SIGNAL AT THE INTERSECTION OF W. LINTON BOULEVARD AND CATHERINE DRIVE/LINTON LAKES DRIVE. (PROJECT NO. 20-001)
Sponsors: Public Works Department
Attachments: 1. Agenda Cover Report, 2. Resolution No. 167-20 - ILA with County to install traffic signal Linton and Catherine, 3. Legal Review ILA with County for installation of new traffic signal at Linton Catherine and Linton Lakes, 4. City of Delray Beach - Interlocal Agreement -W Linton Blvd. and Catharine Dr ybh.9.3.2020 electronic signature pg.ybh
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Missie Barletto, Public Works Director
THROUGH: Jennifer Alvarez, Interim City Manager
DATE: November 17, 2020

Title
RESOLUTION NO.167-20: REQUESTING APPROVAL OF AN INTERLOCAL AGREEMENT (ILA) BETWEEN PALM BEACH COUNTY AND THE CITY OF DELRAY BEACH FOR THE DESIGN AND CONSTRUCTION OF A TRAFFIC SIGNAL AT THE INTERSECTION OF W. LINTON BOULEVARD AND CATHERINE DRIVE/LINTON LAKES DRIVE. (PROJECT NO. 20-001)

Body
Recommended Action:
Recommendation
Motion to Approve Resolution No. 167-20 to approve an Interlocal Agreement (ILA) with Palm Beach County and the City of Delray Beach (City) for the design and construction of a traffic signal at the intersection of W. Linton Boulevard and Catherine Drive/Linton Lakes Drive.

Body
At the City's request, Palm Beach County (County) is installing a traffic signal at the intersection of W. Linton Boulevard and Catherine Drive/Linton Lakes Drive to improve safety at the intersection. The installation of the traffic signal cost is being cost shared 50% by Palm Beach County and 50% by the City. As a condition to install the traffic signal, the County requested that the Catherine Drive approach be improved to include an outbound (southbound) left-turn lane and a wider inbound (northbound) receiving Lane. The City has an executed agreement with a design engineer for these improvements and the design is ongoing. The City is 100% financially responsible for the design and construction of the Catherine Drive approach improvements, estimated at $54,359 and $103,329 respectively for a total of $157,688.

This project has two components, (1) the improvements to Catherine Drive that the City is responsible for designing and constructing and (2) the installation of the traffic signal on W. Linton Boulevard that the County will be designing and installing. The ILA referenced herein is for the County's portion of the project, the design and construction of the traffic signal. The ILA with the County ...

Click here for full text