Title: APPROVE A NO COST TIME EXTENSION AMENDMENT NO. 01 TO GRANT AGREEMENT 46000004358 (CONSIDERED PHASE 2 OF RECLAIMED AREA 10), WITH SOUTH FLORIDA WATER MANAGEMENT DISTRICT FOR PROVIDING SUPPLEMENTARY FUNDING FOR CONSTRUCTION OF RECLAIMED WATER TRANSMISSION ALONG SE 1st AVE, SE 1st ST, SW 1st ST, NE 2nd Ave, AND NE 1st St.
Sponsors: Utilities Department
Attachments: 1. Agenda Cover Report, 2. Legal Review Amd #1 to Grant Agreement with SFWMD Reclaimed Area 10_.pdf, 3. Amd #1 to Agreement No. 4600004358 with SFWMD.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and Commissioners
FROM: Hassan Hadjimiry, P.E., Utilities Director
THROUGH: Terrence R. Moore, ICMA-CM
DATE: September 19, 2022

Title
APPROVE A NO COST TIME EXTENSION AMENDMENT NO. 01 TO GRANT AGREEMENT 46000004358 (CONSIDERED PHASE 2 OF RECLAIMED AREA 10), WITH SOUTH FLORIDA WATER MANAGEMENT DISTRICT FOR PROVIDING SUPPLEMENTARY FUNDING FOR CONSTRUCTION OF RECLAIMED WATER TRANSMISSION ALONG SE 1st AVE, SE 1st ST, SW 1st ST, NE 2nd Ave, AND NE 1st St.

Body
Recommended Action:
Recommendation
Motion to approve and execute amended Grant Agreement (Agreement) No. 46000004358-A01 with the South Florida Water Management District (SFWMD) for providing supplementary funding for construction of reclaimed water transmission main for Area 10 (Phase 2) project, along SE 1st Ave, SE 1st St, SW 1st St, NE 2nd Ave, and NE 1st St, as part of their Cooperative Funding Program for Alternative Water Supply (AWS).

Body
Background:
On November 12, 2020, the SFWMD Board approved a list of grant recipients which included the City of Delray Beach in the amount of $660,000 for the reference project. On May 18, 2021, the City Commission approved Grant Agreement No. 4600004358 for AWS, Reclaimed Water Construction along SE 1st Ave, SE 1st St, SW 1st St, NE 2nd Ave, and NE 1st St. The original term of the Agreement was seven hundred eighteen days (718) days effective November 12, 2020, through October 31, 2022. Pending work under this Agreement has been delayed due to supply chain in receiving materials, and Florida East Coast Railway (FEC) Permit.

The Agreement is being amended to extend the period of performance, revise the Statement of work, and revise the Payment Deliverable Schedule of the Agreement.

The new terms and conditions of the amended Agreement are as follows:

The term of the Agreement is hereby extended by eight (8) months and the expiration date, as amended, is June 30, 2023. Regardless of the actual date of execution, this AMENDMENT NO. 01 shall b...