File #: 18-0697 CRA    Version: 1 Name:
Type: CRA Contract Status: Agenda Ready
File created: 11/4/2020 In control: Community Redevelopment Agency
On agenda: 11/12/2020 Final action:
Title: FIRST AMENDMENT TO THE GROUND LEASE AGREEMENT WITH HATCHER CONSTRUCTION & DEVELOPMENT, INC.
Attachments: 1. Agenda Cover Report, 2. Exhibit A - First Amendment to Lease (Hatcher), 3. Exhibit B - Landscape Maintenance Agreement CIty-CRA, 4. Exhibit C - Preliminary Landscaping Plan, 5. Exhibit D - Letter from Hatcher to CRA
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: CRA Board of Commissioners
FROM: Ivan Cabrera, AICP, Redevelopment Manager
THROUGH: Renée A. Jadusingh, Esq., Executive Director
DATE: November 12, 2020

Title
FIRST AMENDMENT TO THE GROUND LEASE AGREEMENT WITH HATCHER CONSTRUCTION & DEVELOPMENT, INC.

Body
Recommended Action:
Recommendation
Approve the First Amendment to the Ground Lease Agreement with Hatcher Construction & Development, Inc. in substantially the attached form.

Body
Background:
On June 11, 2019, the CRA Board approved a Ground Lease with Hatcher Construction & Development, Inc. (Hatcher) to construct a two-story 6,000 SF office building on two (2) adjacent, vacant CRA-owned parcels located at 20 and 26 NW 6th Avenue (Properties). The Ground Lease was executed on July 18, 2019.

At the November 19, 2019, and December 10, 2019, CRA Board meetings, Hatcher presented preliminary construction elevations and a proposed site-plan for the development of the Properties. At both meetings, the CRA Board provided comments and feedback.

In February 2020, Hatcher submitted a Conditional Use and Class V Site Plan applications to the City of Delray Beach (City) for the development of the Properties. The development proposal consists of the following: construction of two separate 2-story, 3,556 SF commercial buildings for a total of 7,112 SF of office/retail/commercial space. The first floor of each building will have the flexibility to accommodate office/retail/commercial with office space on the second floor of each building.

As the applications are currently going through the City approval process, Hatcher submitted a letter on October 7, 2020, requesting a six (6) month extension to the termination date for the Site Plan Analysis period (the period during which all permits, approvals, licenses must be obtained) from January 18, 2021, to July 18, 2021 due to City review timeframes.

Additionally, part of the applications’ approval process entails complying with the City’s landscaping r...

Click here for full text